Lucky 7 Solar (ERCOT-26INR0409) — Project Summary

Queue ID
ERCOT-26INR0409
Capacity
101.6 MW
Technology
Solar
Status
active
Location
Hopkins, TX
Region
ERCOT
Developer
Lucky 7 Solar Farm LLC
IA Status
IA Executed

Lucky 7 Solar

ERCOT-26INR0409BetaActiveSolarERCOTLBNL + Live

101.6 MW generation in Hopkins, TX · In queue since March 2024 · Proposed COD September 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

101.6 MW

Capacity

1

Components

Solar

2y 8m

In Queue

IA Executed

IA Phase

Signed Aug 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 5m

IA → COD

2y 1m

Total Duration

1y 5m

Construction75%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 13, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-09-20

Queue history
26INR0409 · 30 monthly ERCOT reports, Mar 2024 – Sep 2026

Projected COD moved

2 times

Jul 2026 → Sep 2027

Net change

+14 months

first report to latest

Capacity

101 → 101 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 22, 2024
Facilities study approvedAug 28, 2026
Interconnection agreement signedAug 13, 2025
On ERCOT's inactive listAug 2025 – Aug 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activitypartnershipGlobeNewswire · 2025-08-15

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
—
Developer in saved assessment
Sabanci Renewables
Ownership change in saved research
Status at research time
Active
Active — financing closed June 2026, construction underway targeting Q3 2027 COD
Financing
Secured
Financing closed June 1, 2026 by Sabanci Renewables for Lucky 7 Solar and one other Texas project (combined announcement); specific amount not disclosed in public releases
Ownership history
  1. 2025-08·OCI Energy / OCI Holdings→Sabanci Renewableskoreaherald.com

Milestones in this assessment

IA executedAug 13, 2025

Interconnection Agreement executed with ERCOT

cleanview.co
Ownership changeAug 15, 2025

OCI Energy sold Lucky 7 Solar (100 MWac/130 MWdc) to Sabanci Renewables

sidley.com
Financing closeJun 1, 2026

Sabanci Renewables closed financing for Lucky 7 Solar and second Texas project

newsfilecorp.com
COD targetundefined 2027Latest in this assessment

Expected commercial operation date Q3 2027 per developer

sabanciclimatetech.com
Research sources and reasoning (7 recorded sources)

high confidence at research time

  1. newsfilecorp.com/release/299626/Sabanci-Renewables-Closes-Financing-for-Two-Texas-Solar-Projects
  2. chosun.com/english/industry-en/2026/01/19/Z62YZFMXIBDLBLSZODL33O26IU/
  3. powermag.com/texas-solar-projects-move-forward-under-new-leadership/
  4. koreaherald.com/article/10556938
  5. sabanciclimatetech.com/en/renewables/project-detail/Lucky-7-Solar-Farm-LLC/15/31/0
  6. sidley.com/en/newslanding/newsannouncements/2025/08/sidley-represents-oci-in-sale-of-texas-utility-scale-solar-project-lucky-7-to-sabanci-renewables
  7. cleanview.co/planned-solar-projects/TX/26INR0409/lucky-7-solar

Commercial operation date: LBNL proposed COD of 2027-09-20 aligns with Sabanci Renewables' official project page stating 'expected to reach COD in Q3 2027' and multiple press releases from Aug 2025 confirming the same timeline post-acquisition.

Developer: LBNL filing entity 'Lucky 7 Solar Farm LLC' is the project SPV. Original developer OCI Energy sold the project to Sabanci Renewables in August 2025, confirmed by multiple sources including Korea Herald, Sidley legal announcement, and Sabanci's own project page.

Status: LBNL status 'active' with IA executed Aug 2025 is accurate. Sabanci Renewables closed project financing in June 2026 per TMX Newsfile, indicating active development phase with construction progressing toward 2027 COD.

Project lifecycle
as of 2025-08-15
OperationalNoGlobeNewswire · 2025-08-15
TechnologySolarGlobeNewswire · 2025-08-15
DeveloperOCI Energy, Sabanci RenewablesGlobeNewswire · 2025-08-15

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Lucky 7 Solar is a proposed 100.8 MW solar generation project located in Hopkins County, Texas. The developer is OCI SOLAR POWER LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0409, with a queue entry date of March 22, 2024, and a proposed commercial operation date of September 20, 2027. Its interconnection status is currently in the Facility Study phase.

The Lucky 7 Solar project has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Hopkins

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Lucky 7 Solar Farm LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 2621 Sandy Ranch Switch - 2464 CASH SWITCH

Data Source

LBNL + Live

PartnerSabanci RenewablesGlobeNewswire · 2025-08-15
CompanyOCI EnergyGlobeNewswire · 2025-08-15
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-09