Rock Creek BESS
251.05 MW storage in Kendall, TX · In queue since February 2024 · Proposed COD March 2028
251.05 MW
Capacity
1
Components
Battery
2y 9m
In Queue
IA Executed
IA Phase
Signed Jul 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 5m
IA → COD
2y 8m
Total Duration
1y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2028-03-29
Projected COD moved
3 times
Jun 2026 → Mar 2028
Net change
+21 months
first report to latest
Capacity
251 MW
unchanged in the reports
Latest stage
Cancelled
last listed Dec 2025
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Developer cancelled project after local opposition in Comfort, TX
boernestar.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- boernestar.com/article/12569,battery-storage-firm-ends-plans-for-comfort-site
- mysanantonio.com/business/article/texas-hill-country-battery-storage-project-pulled-21319672.php
- interconnection.fyi/project/ercot-26inr0407
- jasonisaac.substack.com/p/a-texas-community-just-popped-the
- reataranchrealty.com/blog/fight-against-battery-farms-in-the-texas-hill-country
Commercial operation date: Project was withdrawn in January 2026 before construction began, rendering the LBNL proposed COD of 2028-03-29 moot. No alternative COD exists.
Developer: LBNL filing entity is 'Flat Rock Energy Center, LLC' (project-specific LLC). MySA article (Feb 1, 2026) identifies 'East Point Energy' as the company that abandoned the project, indicating East Point Energy is the parent/operating company.
Status: Multiple sources confirm cancellation: Boerne Star (Jan 27, 2026) reports company 'canceling plans'; MySA (Feb 1, 2026) states 'East Point Energy has abandoned' the project; interconnection.fyi shows status as 'withdrawn'; Jason Isaac Substack (Feb 5, 2026) calls it 'the first time in Texas, a battery energy storage system project has been stopped cold by local opposition.'
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Rock Creek BESS is a proposed 251.05 MW battery storage project located in Kendall County, Texas. Developed by Flat Rock Energy Center, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-26INR0407 on February 27, 2024. Its proposed commercial operation date is December 1, 2026, and its interconnection status is currently in the Facility Study phase.
The Rock Creek BESS development has been featured in recent industry news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Dec 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Kendall
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Flat Rock Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7150 Kendall 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HHOLLW2_WND1
- POI Substation
- Horse Hollow Kendall Tie
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.