AGGIE STORAGE PROJECT SLF (ERCOT-26INR0389) — Project Summary

Queue ID
ERCOT-26INR0389
Capacity
—
Technology
Battery
Status
active
Location
Reeves, TX
Region
ERCOT
Developer
reNRG TX 8 LLC
IA Status
—

AGGIE STORAGE PROJECT SLF

ERCOT-26INR0389BetaActiveOtherBattery Energy StorageERCOTLive · ERCOT

— hybrid in Reeves, TX · In queue since February 2024 · Proposed COD November 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

—

Capacity

0

Components

2y 8m

In Queue

—

IA Status

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 9m

Pre-Study0%
Queue EntryFeb 2, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-11-30

About

The Aggie Storage Project SLF (queue ID ERCOT-26INR0389) is a proposed battery energy storage development project in Reeves County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by reNRG TX 8 LLC. It is classified as a hybrid project, with technology components listed as battery energy storage and an additional component categorized as "Other." The provided data does not specify total capacity or the capacities of the individual components.

The project entered the ERCOT interconnection queue on February 2, 2024, and its queue status is active. Its proposed point of interconnection is the Coyote Springs Substation at 138 kV (bus number 38113), located at approximately 31.396675, -103.6252777 in Reeves County. The project has a proposed commercial operation date of November 30, 2027. The available data does not indicate the status of an interconnection agreement.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Reeves

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

reNRG TX 8 LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

POI: COYOTE SPRINGS SUBSTATION - 138KV BUS NUMBER: 38113 POI LOCATION: 31.396675, -103.6252777 COUNTY: REEVES

Data Source

Live · ERCOT

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about AGGIE STORAGE PROJECT SLF