Nanulak BESS
181.54 MW storage in Reeves, TX · In queue since March 2024 · Proposed COD June 2027
181.54 MW
Capacity
1
Components
Battery
2y 8m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
Projected COD moved
3 times
Dec 2026 → Jun 2027
Net change
+6 months
first report to latest
Capacity
180 → 182 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
ERCOT Standard Generation Interconnection Agreement filing with Texas-New Mexico Power Company
interchange.puc.texas.govResearch sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/planned-battery-projects/TX/26INR0385/nanulak-bess
- interchange.puc.texas.gov/Search/Filings?ControlNumber=35077&ItemMatch=0&SortBy=ItemNumber&SortOrder=Descending
- ercotqueue.com/project/26INR0385
Commercial operation date: LBNL queue snapshot shows proposed COD of March 2027. No independent news sources or press releases found to validate or contradict this date.
Developer: Only the project-LLC 'Nanulak BESS, L.L.C.' appears in LBNL filing and PUC filings. No press releases, corporate announcements, or news coverage identify a parent operating company or developer.
Status: LBNL shows 'active' status in Facility Study phase. PUC filings from November 2025 reference pending ERCOT Standard Generation Interconnection Agreement with TNMP, confirming active interconnection process.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Nanulak BESS is a proposed battery energy storage development project located in Reeves County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by Nanulak BESS, L.L.C. and has a total proposed capacity of 181.54 megawatts (MW), consisting entirely of battery storage. It is planned to connect to the grid at the TNCOYOTSPG1 138 kV point of interconnection (bus 38113).
The project is listed in the ERCOT interconnection queue under the identifier 26INR0385. It entered the queue on March 22, 2024, and its status is active. Nanulak BESS is currently at the Facility Study stage of the interconnection process and has not yet executed an interconnection agreement. The developer has proposed a commercial operation date of June 30, 2027.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Nanulak BESS, L.L.C.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
38113 TNCOYOTSPG1 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.