Pollo Pinto Solar
150.8 MW generation in Palo Pinto, TX · In queue since February 2024 · Proposed COD August 2027
150.8 MW
Capacity
1
Components
Solar
2y 5m
In Queue
Facility Study
IA Phase
COD target: 2027
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-15
The Pollo Pinto Solar project is a proposed solar generation facility with a total capacity of 150.8 MW. It is located in Palo Pinto County, Texas, and is being developed by TX Palo Pinto SB 6, LLC. The project is interconnected within the Electric Reliability Council of Texas (ERCOT) queue under queue ID ERCOT-26INR0364, with an interconnection queue entry date of February 27, 2024.
The proposed commercial operation date (COD) for Pollo Pinto Solar is August 15, 2027. Its interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is Tap 138kV 331 RWMILLER - 320 JAYBIRD. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Palo Pinto
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
TX Palo Pinto SB 6, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 331 RWMILLER - 320 JAYBIRD
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Pollo Pinto SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.