Saint Charles Energy Storage (ERCOT-26INR0363) — Project Summary

Queue ID
ERCOT-26INR0363
Capacity
202.7 MW
Technology
Battery
Status
active
Location
Houston, TX
Region
ERCOT
Developer
RSN STORAGE 001, LLC
IA Status
Facility Study

Saint Charles Energy Storage

ERCOT-26INR0363BetaActiveBatteryERCOTLBNL + Live

202.7 MW storage in Houston, TX · In queue since February 2024 · Proposed COD April 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

202.7 MW

Capacity

1

Components

Battery

2y 9m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 2m

Facilities Study50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-04-16

Queue history
26INR0363 · 19 monthly ERCOT reports, Mar 2025 – Sep 2026

Projected COD moved

2 times

Jun 2026 → Apr 2029

Net change

+34 months

first report to latest

Capacity

254 → 203 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 27, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Apr 16, 2029
From queue filing
Developer in saved assessment
—
From queue filing
Status at research time
Active
Active — early-stage Facility Study phase with no public development announcements
Financing
Not recorded

Milestones in this assessment

IA executedLatest in this assessment

Project in Facility Study phase, no IA executed

cleanview.co
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0363/saint-charles-energy-storage
  2. interconnection.fyi/projects/state/TX
  3. ercotqueue.com/project/26INR0363

Commercial operation date: Only LBNL queue data provides a COD target of April 2029. No news articles or press releases mention this specific project or provide alternative timeline information.

Developer: LBNL lists 'RSN STORAGE 001, LLC' which appears to be a project-specific shell entity. No search results identify the parent operating company or developer behind this LLC.

Status: LBNL status is 'active' at Facility Study stage (no IA executed yet). No news coverage exists to indicate construction activity, financing, or other milestones.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Saint Charles Energy Storage is a proposed battery energy storage project in Houston County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The development project is being advanced by RSN STORAGE 001, LLC and has a total planned capacity of 202.7 megawatts (MW), consisting entirely of battery storage. The project is designed to interconnect to the grid via a tap on the 138 kV transmission line between the FLATBRA_8 (3345) and JIM_ENG_8 (3351) buses.

The project is listed in the ERCOT interconnection queue under queue ID 26INR0363 and holds an active status. It entered the queue on February 27, 2024, and is currently at the Facility Study stage of the interconnection process. Its proposed commercial operation date is April 16, 2029.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Houston

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

RSN STORAGE 001, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

TAP 138kV 3345 FLATBRA_8 - 3351 JIM_ENG_8

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.