Megamouth Energy Storage
101.3 MW storage in Harris, TX · In queue since March 2024 · Proposed COD December 2028
101.3 MW
Capacity
1
Components
Battery
2y 8m
In Queue
IA Executed
IA Phase
Signed Nov 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 8m
IA → COD
3y 1m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-12-31
Projected COD moved
3 times
Jun 2026 → Dec 2028
Net change
+30 months
first report to latest
Capacity
101 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
- 2026-03·Grid Connected Infrastructure (GCI Megamouth, LLC)→Banpu Power USprnewswire.com
Milestones in this assessment
Banpu Power US acquired 100 MW Megamouth BESS project from Grid Connected Infrastructure for $90M investment
prnewswire.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- prnewswire.com/news-releases/grid-connected-infrastructure-sells-100-mw-megamouth-battery-energy-storage-project-in-houston-to-banpu-power-us-302722650.html
- mercomcapital.com/grid-connected-infrastructure-sells-100-mw-megamouth-bess-in-houston/
- asia.nikkei.com/business/energy/thailand-s-banpu-power-plans-90m-energy-storage-project-in-us
- bangkokpost.com/business/general/3189125/banpu-acquires-battery-farm-in-us
- energy-storage.news/arevon-starts-building-1gwh-california-bess-bpp-and-energy-vault-buy-texas-projects/
Commercial operation date: LBNL shows 2028-12-31 COD, but March 2026 acquisition announcements by Banpu Power indicate near-term development with typical 12-18 month construction timelines for 100 MW BESS projects, suggesting 2027 target more realistic than end-2028.
Developer: LBNL filing entity is GCI Megamouth, LLC (Grid Connected Infrastructure project LLC). Multiple March 2026 sources confirm GCI sold the project to Banpu Power US, making Banpu the current owner/developer.
Status: LBNL status is Active with IA executed November 2025. Acquisition closed March 2026 per multiple sources. No construction start announced yet, consistent with pre-construction development phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed Megamouth Energy Storage project is a 101.3 MW battery storage facility located in Harris County, Texas. Developed by GCI Megamouth, LLC, the project entered the ERCOT interconnection queue as ERCOT-26INR0341 on March 22, 2024. The current proposed commercial operation date is December 31, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 42750 Mykawa 138 kV location. The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
GCI Megamouth, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
42750 Mykawa 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.