Pianissimo BESS II
202 MW storage in Wise, TX · In queue since November 2024 · Proposed COD December 2027
202 MW
Capacity
1
Components
Battery
2 years
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Projected COD moved
1 time
Sep 2026 → Dec 2027
Net change
+15 months
first report to latest
Capacity
201 → 202 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Original proposed completion date before revision to Dec 2027
interconnectionfyi.substack.comRevised proposed completion date per Feb 2025 queue update
interconnectionfyi.substack.comResearch sources and reasoning (3 recorded sources)
low confidence at research time
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-442
- interconnection.fyi/project/ercot-26inr0329
- ercotqueue.com/project/26INR0329
Commercial operation date: LBNL queue shows 2027-12-31 COD. Interconnection Weekly (Feb 2025) notes the proposed completion changed from Sept 2026 to Dec 2027, confirming the current LBNL date is the latest available target. No independent developer announcements found.
Developer: Only source is LBNL filing entity 'Pianissimo Storage, LLC'. No press releases, corporate announcements, or parent company identification found in search results. All aggregator sites echo the LBNL entity name.
Status: LBNL shows 'active' status at Facility Study stage with no IA date. ERCOTqueue.com assigns 5% build-chance, indicating early-stage development with no financing or construction signals.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Pianissimo BESS II is a proposed 202 MW battery storage project located in Wise County, Texas. The project, developed by Pianissimo Storage, LLC, is interconnected within the ERCOT region under queue ID ERCOT-26INR0329. It entered the interconnection queue on November 19, 2024, and has a proposed commercial operation date of December 31, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists entirely of battery storage, with a total capacity of 202 MW. The point of interconnection is Tap 138kV 685 LEO - 587 GREENWOOD. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wise
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pianissimo Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 685 LEO - 587 GREENWOOD
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.