Misty Hollow BESS
245.8 MW storage in Grimes, TX · In queue since December 2023 · Proposed COD July 2028
245.8 MW
Capacity
1
Components
Battery
2y 11m
In Queue
IA Executed
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2 years
IA → COD
2y 7m
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-07-15
Projected COD moved
1 time
Dec 2026 → Jul 2028
Net change
+19 months
first report to latest
Capacity
205 → 246 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Interconnection agreement executed with CenterPoint Energy Houston Electric
interchange.puc.texas.govProposed completion date revised from November 2026 to July 2028
interconnectionfyi.substack.comResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ercot.com/files/docs/2026/01/08/Capacity-Changes-by-Fuel-Type-Charts_December_2025.xlsx
Commercial operation date: LBNL queue shows July 2028 COD. Interconnection.fyi confirms the project's proposed completion changed from Nov 2026 to July 14, 2028, corroborating the LBNL date. No developer announcements found to contradict this timeline.
Developer: All sources consistently identify Clear Fork BESS, LLC as the developer. No parent company or operating entity identified in search results. This appears to be the actual developer rather than a shell LLC, as no alternative corporate structure was found.
Status: LBNL shows IA executed on 2025-12-04. Texas PUC filings from December 2025 confirm interconnection agreement filings between CenterPoint Energy Houston Electric and Clear Fork BESS for Misty Hollow BESS, validating the IA execution status.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Misty Hollow BESS project is a proposed 245.8 MW battery storage project located in Grimes County, Texas. Developed by Clear Fork BESS, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-26INR0324 on December 20, 2023. The current interconnection status is Facility Study, and the proposed commercial operation date is July 15, 2028.
The project consists entirely of battery storage, with a total capacity of 245.8 MW. The point of interconnection is the 345 kV Singleton substation (#44645). The project is currently listed as active within the ERCOT queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Grimes
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Clear Fork BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Singleton (#44645)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Misty Hollow BESS
Data-driven briefing on Misty Hollow BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.