Windmill Ridge Storage
151.4 MW storage in Brazoria, TX · In queue since November 2023 · Proposed COD December 2026
151.4 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
Projected COD moved
1 time
May 2026 → Dec 2026
Net change
+7 months
first report to latest
Capacity
151 MW
unchanged in the reports
Latest stage
Cancelled
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Project cancelled and removed from ERCOT queue, listed among 43 cancelled ERCOT projects in April 2026
facebook.comResearch sources and reasoning (3 recorded sources)
high confidence at research time
- interconnection.fyi/project/ercot-26inr0321
- lorenz-g.github.io/tesla-megapack-tracker/gov-us-eia.html
- facebook.com/groups/erathcountystopsolarfarmshere/posts/1908133659896313/
Commercial operation date: LBNL proposed COD of 2026-12-31 exists, but multiple independent sources (interconnection.fyi, EIA data tracker, Facebook ERCOT list) confirm project was cancelled/withdrawn in April 2026, making the original COD target moot.
Developer: Only LBNL filing entity 'BT WMR Storage, LLC' is available. No press releases, corporate announcements, or news coverage identify a parent operating company. The 'BT' prefix suggests a shell LLC but no parent entity could be determined from available sources.
Status: While LBNL snapshot shows 'active' status from November 2023, three independent sources (interconnection.fyi, EIA data tracker showing 'cancelled', and Facebook post citing ERCOT April 2026 cancelled projects list) confirm withdrawal occurred in April 2026.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Windmill Ridge Storage is a proposed 151.4 MW battery storage project located in Brazoria County, Texas. The developer is BT WMR Storage, LLC. The project is interconnected to the ERCOT grid under queue ID ERCOT-26INR0321, with a queue entry date of November 14, 2023, and a proposed commercial operation date of December 31, 2026. Its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Windmill Ridge Storage operating plant (EIA plant ID 68177). It has also been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Mar 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT WMR Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Angleton (Bus #42110) - West Columbia Local (Bus #43381) 138 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.