Quantum Storage
321.75 MW generation in Haskell, TX · In queue since March 2024 · Proposed COD September 2026
321.75 MW
Capacity
1
Components
Battery
2y 8m
In Queue
IA Executed
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 6m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2026-09-01
Projected COD moved
4 times
Mar 2026 → Sep 2026
Net change
+6 months
first report to latest
Capacity
321 → 322 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- intersect.com/portfolio/quantum
- cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0310/quantum-storage
- ercotqueue.com/project/26INR0310
- interconnection.fyi/project/ercot-26inr0310
Commercial operation date: No independent post-LBNL source gives a different date. Cleanview says 'Expected online 2026' and interconnection.fyi lists a proposed completion of September 1, 2026, but both appear to mirror queue data rather than a developer-announced target.
Developer: The Intersect portfolio page has a 'Quantum' project entry about co-locating supply with data center load in Texas. This matches the 'IP Quantum II BESS, LLC' filing entity, whose 'IP' prefix points to Intersect Power. The search results do not show any ownership change.
Status: LBNL lists status active with IA Executed, and nothing in the search results contradicts this. The ercotqueue.com 'Commissioned' flag is ambiguous and uncorroborated, so I did not upgrade the status to Online.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed Quantum Storage project is a 321.06 MW battery storage development in Haskell County, Texas. The project, developed by IP Quantum II BESS, LLC, is located within the ERCOT region and has interconnection queue ID ERCOT-26INR0310.
The project entered the ERCOT interconnection queue on March 22, 2024, with a proposed commercial operation date of June 1, 2026. The interconnection agreement for the project was executed on October 26, 2023. The point of interconnection is the 60089 Kilby Switching Station 345kV.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Haskell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Quantum II BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60089 Kilby Switching Station 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- RN_QTUM_SLR
- POI Substation
- Solara Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.