Carolina Storage Young County (ERCOT-26INR0302) — Project Summary

Queue ID
ERCOT-26INR0302
Capacity
104.5 MW
Technology
Battery
Status
active
Location
Young, TX
Region
ERCOT
Developer
CSE Storage, LLC
IA Status
Facility Study

Carolina Storage Young County

ERCOT-26INR0302BetaActiveBatteryERCOTLBNL + Live

104.5 MW storage in Young, TX · In queue since February 2024 · Proposed COD August 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

104.5 MW

Capacity

1

Components

Battery

2y 9m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 6m

Facilities Study50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-01

Queue history
26INR0302 · 32 monthly ERCOT reports, Feb 2024 – Sep 2026

Projected COD moved

3 times

Dec 2025 → Aug 2028

Net change

+32 months

first report to latest

Capacity

104 → 105 MW

changed in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 27, 2024
Facilities study approvedJul 13, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Aug 1, 2028
From queue filing
Developer in saved assessment
CSE Storage, LLC
From queue filing
Status at research time
Active
Active — Facility Study stage; Young County Commissioners Court considering reinvestment zone and tax abatement as of December 2025
Financing
Not recorded

Milestones in this assessment

Permit approvedDec 2025Latest in this assessment

Young County Commissioners Court scheduling consideration of reinvestment zone and tax abatement for battery storage project

grahamleader.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. interconnection.fyi/project/ercot-26inr0302
  2. cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0302/carolina-storage-young-county
  3. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-db7
  4. grahamleader.com/news/dates-set-reinvestment-zone-abatement-consideration-solar-battery-project

Commercial operation date: LBNL queue snapshot shows proposed COD of August 1, 2028. One interconnection.fyi update mentions a COD change from September 2027 to July (year unspecified), but no authoritative recent press releases or developer announcements confirm a different target. Defaulting to LBNL filing date.

Developer: All sources consistently identify 'CSE Storage, LLC' as the developer. No parent company, operating entity, or ownership change information found in search results. Entity appears to be the actual developer rather than a shell LLC.

Status: LBNL shows 'active' status in Facility Study phase. December 2025 local news confirms the project is advancing through county approval processes for tax incentives, indicating active development.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Carolina Storage Young County project is a proposed 104.4 MW battery storage project located in Young County, Texas. The developer is CSE STORAGE, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0302, with a queue entry date of February 27, 2024. The proposed commercial operation date is August 1, 2028.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is at the TAP 138 KV BUS, creating a new bus between Murray (792) and Graham SES (1431).

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Young

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

CSE Storage, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

TAP 138 KV BUS AND CREAT NEW BUS BETWEEN MURRAY (792) AND GRAHAM SES (1431) COUNTY : YOUNG

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.