Bhalu Storage
205.5 MW storage in Howard, TX · In queue since October 2023 · Proposed COD April 2028
205.5 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-21
Projected COD moved
5 times
Aug 2026 → Apr 2028
Net change
+20 months
first report to latest
Capacity
206 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
USACE aquatic resources delineation report filed for Howard County site
swf.usace.army.milProposed completion date updated to May 5, 2028 (from March 2, 2027)
interconnectionfyi.substack.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0301/bhalu-storage
- interconnection.fyi/project/ercot-26inr0301
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-ad5
- swf.usace.army.mil/Portals/47/docs/regulatory/JDs/2024/SWF-2024-00496%20AJD.pdf?ver=ybHF10N_a_e-jXNt80h69A%3D%3D
- bizapedia.com/tx/bhalu-storage-llc.html
Commercial operation date: LBNL proposed COD was April 2028. Interconnection.fyi project update from April 2025 reports proposed completion changed from March 2027 to May 2028, indicating a recent schedule adjustment. Consensus is May 2028 based on most recent queue update.
Developer: All sources consistently identify 'Bhalu Storage, LLC' as the developer. No parent company or operating entity identified in search results. Texas LLC filing confirms entity organized September 2024, but no corporate parent disclosed.
Status: LBNL shows 'Active' status in Facility Study phase. USACE jurisdictional determination from October 2024 confirms active site preparation and environmental review, consistent with pre-construction development phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Bhalu Storage is a proposed 205.5 MW battery storage project located in Howard County, Texas. Developed by Bhalu Storage, LLC, the project consists entirely of battery storage. It is listed in the ERCOT interconnection queue as entry ERCOT-26INR0301, with a queue entry date of October 30, 2023, and a proposed commercial operation date of April 21, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Bhalu operating plant (EIA ID 67652). The point of interconnection is Tap 138kV Bulldog (#23833) _x0013_ Elbow (#23834). The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Howard
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bhalu Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Bulldog (#23833) – Elbow (#23834)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- POI Substation
- Salem Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Bhalu Storage
Data-driven briefing on Bhalu Storage — fleet, generation, financial, and news signals.
Bhalu
Data-driven briefing on Bhalu — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.