Camino Ranch Storage 2 SLF
238.45 MW generation in Houston, TX · In queue since February 2024 · Proposed COD December 2028
238.45 MW
Capacity
1
Components
Battery
2y 5m
In Queue
Facility Study
IA Phase
Signed Dec 2025
Queue → IA
1y 10m
IA → COD
3 years
Total Duration
1y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-09
The Camino Ranch Storage 2 SLF project is a proposed 238.45 MW battery storage project located in Houston County, Texas. The project, developed by Camino Ranch Solar LLC, is interconnected within the ERCOT region under queue ID ERCOT-26INR0257. It entered the queue on February 2, 2024, and has a proposed commercial operation date of December 9, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists solely of battery storage, with a total capacity of 238.45 MW. The point of interconnection is Tap to Jim English (#3351) _x0013_ Flat Branch (#3345) 138kV. The project is currently listed as active within the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Houston
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Camino Ranch Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap to Jim English (#3351) – Flat Branch (#3345) 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Camino Ranch Storage 2 SLFForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.