Neutron Storage
104.5 MW storage in Mclennan, TX · In queue since September 2023 · Proposed COD April 2028
104.5 MW
Capacity
1
Components
Battery
2y 10m
In Queue
IA Executed
IA Phase
Signed Dec 2025
Queue → IA
2y 3m
IA → COD
2y 4m
Total Duration
2y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2028-04-29
The Neutron Storage project is a proposed 104.36 MW battery energy storage system located in McLennan County, Texas. The project, developed by Neutron Storage, is interconnected within the ERCOT region and entered the ERCOT interconnection queue as ERCOT-26INR0252 on September 8, 2023. Its proposed commercial operation date is April 29, 2028, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists entirely of battery storage, with a total capacity of 104.36 MW. The point of interconnection is the Tap 345kV 13405 Trading House - 68090 Sam Switch. The project is currently listed as active within the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Mclennan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Elawan Neutron Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 13405 Trading House - 68090 Sam Switch
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Neutron StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.