Sengun BESS
200.89 MW storage in Nueces, TX · In queue since January 2024 · Proposed COD March 2028
200.89 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-17
Projected COD moved
1 time
Jan 2026 → Mar 2028
Net change
+26 months
first report to latest
Capacity
201 MW
unchanged in the reports
Latest stage
Cancelled
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Original proposed completion date before being pushed to March 2028
interconnectionfyi.substack.comProject cancelled by developer, removed from ERCOT queue
facebook.comResearch sources and reasoning (4 recorded sources)
high confidence at research time
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-db7
- ercotqueue.com/developer/brp-blue-topaz-12-llc
- facebook.com/groups/erathcountystopsolarfarmshere/posts/1908133659896313/
- interconnection.fyi/project/ercot-26inr0248
Commercial operation date: LBNL queue shows proposed COD of 2028-03-17. Interconnection.fyi notes the date changed from Jan 2026 to Mar 2028, but no independent developer announcement or press release confirms current target. Using LBNL as sole source.
Developer: All sources consistently reference 'BRP Blue Topaz 12, LLC' as developer. No parent company or operating entity identified in search results. Appears to be project-specific LLC but no parent disclosed.
Status: LBNL shows 'active' but multiple independent sources (interconnection.fyi, ercotqueue.com, Facebook community tracking) indicate project status changed to 'Withdrawn' or 'Dropped' by April-May 2026. Ercotqueue.com explicitly labels it 'Dropped'.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Sengun BESS project is a proposed 200.89 MW battery storage project located in Nueces County, Texas. The developer is BRP Blue Topaz 12, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0248, with a queue entry date of January 3, 2024. The proposed commercial operation date is March 17, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the WEST_OSO4A (8484) 138 KV substation. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Mar 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Nueces
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Blue Topaz 12, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
WEST_OSO4A (8484) 138 KV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.