Energy City BESS (ERCOT-26INR0231) — Project Summary

Queue ID
ERCOT-26INR0231
Capacity
204.9 MW
Technology
Battery
Status
active
Location
Midland, TX
Region
ERCOT
Developer
Energy City BESS LLC
IA Status
Facility Study

Energy City BESS

ERCOT-26INR0231BetaActiveBatteryERCOTLBNL + Live

204.9 MW storage in Midland, TX · In queue since October 2023 · Proposed COD May 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

204.9 MW

Capacity

1

Components

Battery

3y 1m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 7m

Facilities Study50%
Queue EntryOct 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-05-07

Queue history
26INR0231 · 37 monthly ERCOT reports, Sep 2023 – Sep 2026

Projected COD moved

3 times

Jul 2026 → May 2029

Net change

+34 months

first report to latest

Capacity

205 MW

unchanged in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 4, 2023
Facilities study approvedMar 20, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jun 30, 2027
Differs from queue: May 7, 2029From queue filing
Developer in saved assessment
Energy City BESS LLC
From queue filing
Status at research time
Active
Active — Facility Study stage per LBNL queue, no public construction or financing announcements found
Financing
Not recorded
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. cleanview.co/planned-battery-projects/TX/26INR0231/energy-city-bess
  2. cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0231/energy-city-bess
  3. modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx

Commercial operation date: LBNL queue snapshot shows June 2027 COD. No project-specific news or press releases found to validate or contradict this date. Search results discuss other Texas BESS projects (Alamo City, Red Egret) but none mention Energy City BESS specifically.

Developer: Only source is LBNL filing showing 'Energy City BESS LLC' as developer. No news coverage, press releases, or corporate announcements found to identify a parent company or operating entity behind this project-specific LLC.

Status: LBNL shows 'active' status in Facility Study phase. No contradicting evidence or advancement signals found in search results.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Energy City BESS project is a proposed 204.9 MW battery storage project located in Midland County, Texas. Developed by Energy City BESS LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0231, with a queue entry date of October 4, 2023. The project's proposed commercial operation date is June 30, 2027, and its interconnection agreement status is currently in the Facility Study phase.

The point of interconnection for the Energy City BESS project is Tap 138kV 1179 Texaco Mabee Tap - 1200 Mariensfield. The project has appeared in recent news coverage regarding energy storage developments in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Midland

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Energy City BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 1179 Texaco Mabee Tap - 1200 Mariensfield

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Texaco Mabee Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.