Titus Sienta Solar (ERCOT-26INR0230) — Project Summary

Queue ID
ERCOT-26INR0230
Capacity
501.93 MW
Technology
Solar
Status
active
Location
Pecos, TX
Region
ERCOT
Developer
Sol Sienta Solar, LLC
IA Status
Facility Study

Titus Sienta Solar

ERCOT-26INR0230BetaActiveSolarERCOTLBNL + Live

501.93 MW generation in Pecos, TX · In queue since October 2023 · Proposed COD April 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

501.93 MW

Capacity

1

Components

Solar

3y 1m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 6m

Facilities Study50%
Queue EntryOct 13, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-04-19

Queue history
26INR0230 · 35 monthly ERCOT reports, Oct 2023 – Sep 2026

Projected COD moved

3 times

Dec 2026 → Apr 2029

Net change

+28 months

first report to latest

Capacity

409 → 502 MW

changed in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 13, 2023
Facilities study approvedFeb 27, 2026
On ERCOT's inactive listAug 2026 – Aug 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jun 2028
Differs from queue: Apr 19, 2029
Developer in saved assessment
Titus Low Carbon Ventures
Filed as Sol Sienta Solar, LLC
Status at research time
Active
Active in the ERCOT queue at the Facility Study stage with no IA executed. Aggregators disagree: ercotqueue.com labels it 'Construction' and an interconnection.fyi title says 'suspended'. Neither is supported by other evidence.
Financing
Not recorded
Research sources and reasoning (7 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/solar-farms/texas/26INR0230/titus-sienta-solar
  2. cleanview.co/planned-solar-projects/TX/26INR0230/titus-sienta-solar
  3. ercotqueue.com/project/26INR0230
  4. interconnection.fyi/project/ercot-26inr0230
  5. prnewswire.com/news-releases/titus-low-carbon-ventures-secures-initial-673-mw-toward-multi-gigawatt-thermal-program-for-texas-data-center-sites-302554465.html
  6. tituslcv.com/
  7. bizapedia.com/tx/sol-sienta-solar-llc.html

Commercial operation date: Cleanview's two listings of this project say 'expected online June 2028' and 'Expected online 2028', versus the LBNL/ERCOT proposed COD of 2029-04-19. This is about a 10-month gap. Both signals come from one aggregator and no developer statement confirms the date, so the evidence is weak.

Developer: This is inferred, not confirmed. 'Titus' is in the project name, and Sol Sienta Solar, LLC is registered in Fort Worth, where Titus LCV is also based. No source explicitly links the LLC to Titus LCV. Sol Sienta Solar, LLC is a single-project entity on ERCOT's queue.

Status: The LBNL status is 'active' and the interconnection.fyi full text also says active. IA status is Facility Study with no IA date, and no source shows a groundbreaking or permit, so the 'Construction' label is not credible.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Titus Sienta Solar project is a proposed 501.93 MW solar generation facility located in Pecos County, Texas. The project, developed by Sol Sienta Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0230, with a queue entry date of October 13, 2023. The proposed commercial operation date is June 1, 2028.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Tap 138kV 1239 Coyanosa - 11238 Blair Lake Sub. The Titus Sienta Solar project has appeared in recent news coverage regarding renewable energy development in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Pecos

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Sol Sienta Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 1239 Coyanosa - 11238 Blair Lake Sub

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Coyanosa Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.