Titus Low Carbon Ventures Solar 1
338.04 MW generation in San Patricio, TX · In queue since October 2023 · Proposed COD October 2028
338.04 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5 years
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-16
Projected COD moved
2 times
Dec 2026 → Oct 2028
Net change
+22 months
first report to latest
Capacity
287 → 338 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
AEP Texas filed the ERCOT standard generation interconnection agreement with Vaquero Solar (Titus Low Carbon Ventures Solar 1) with the Texas PUC. This is the filing date, not a confirmed signing date.
interchange.puc.texas.govResearch sources and reasoning (6 recorded sources)
medium confidence at research time
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2509
- cleanview.co/power-projects/planned/solar-farms/texas/26INR0211/titus-low-carbon-ventures-solar-1
- interconnection.fyi/project/ercot-26inr0211
- ercotqueue.com/project/26INR0211
- app.nrgmap.com/queues/ercot-26inr0211
- grahamleader.com/news/county-hosting-solar-farm-town-hall-november
Commercial operation date: Only the LBNL/ERCOT proposed COD of 2028-10-16 exists. Cleanview's 'Expected online 2028' and interconnection.fyi's October 2028 date appear to be derived from the same queue data, so they are not independent confirmation. No developer press release or news article gives a different COD.
Developer: LBNL lists the filing entity Vaquero Solar, LLC. A June 2026 Texas PUC filing of the AEP Texas interconnection agreement names 'Vaquero Solar' for the 'Titus Low Carbon Ventures Solar 1' project, so Vaquero is the project vehicle and Titus is the operating developer. The Young County article names Titus, but Young County is far from San Patricio County, so it may concern a different Titus project.
Status: The PUC informational filing of the ERCOT standard generation interconnection agreement (Case 35077-2509) implies the IA exists. ercotqueue.com still shows 'IA, FIS pending' and nrgmap shows 'active', so those sources may be lagging. interxdata's 'operational' label conflicts with every other source and is disregarded.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Titus Low Carbon Ventures Solar 1 is a proposed solar generation project located in San Patricio County, Texas, with a total capacity of 286.84 MW. Developed by Vaquero Solar, LLC, the project consists entirely of solar photovoltaic generation. It is currently in the ERCOT interconnection queue as entry ERCOT-26INR0211, with a queue entry date of October 13, 2023, and a proposed commercial operation date of October 16, 2028. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection is Tap 345kV 8249 Angstrom - 8624 Grissom. The Titus Low Carbon Ventures Solar 1 project has been mentioned in recent news coverage related to industry, deals, and development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
San Patricio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Vaquero Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 8249 Angstrom - 8624 Grissom
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Angstrom Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.