TRIFECTA Gas
453 MW generation in Midland, TX · In queue since June 2023 · Proposed COD February 2030
453 MW
Capacity
1
Components
Gas
3y 5m
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-02-11
Projected COD moved
2 times
Dec 2027 → Feb 2030
Net change
+26 months
first report to latest
Capacity
453 MW
unchanged in the reports
Latest stage
Cancelled
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: Only the LBNL date exists. A Jan 2026 PUC Texas Interchange filing (ERCOT generation report) lists 'TRIFECTA Gas ... NET Power - Midland - WEST - 02/11/2030', but it appears to come from the same ERCOT queue data, so it is not an independent confirmation. No news or press release gives a developer target date.
Developer: LBNL and the PUC Texas ERCOT report both name NET Power, but both derive from the same queue data. No press release or news confirms the developer, and no shell LLC or ownership change was found.
Status: LBNL lists the project as active at the Facility Study stage. The Jan 2026 PUC Texas Interchange listing shows SS and FIS completed with no IA, which is consistent with an active queue entry that has not yet reached IA execution.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The TRIFECTA Gas project is a proposed 453 MW gas-fired generation project located in Midland County, Texas. Developed by NET Power, the project consists of a single 453 MW gas component. It is listed in the ERCOT interconnection queue as entry ERCOT-26INR0183, with a queue entry date of June 28, 2023, and a proposed commercial operation date of February 11, 2030. The project's interconnection status is currently in the Facility Study phase.
The TRIFECTA Gas project has been the subject of recent news coverage, with 29 articles appearing in the press. These articles primarily focus on industry-related topics, with additional coverage on regulatory and grid-related aspects of the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Mar 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Midland
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NET Power
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 1185 Midland County Northwest Switch (bus #1185) – Midland East (bus #1021) 345 kV Line Ckt 01
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Midland County Northwest Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.