Cape Rich BESS
150.52 MW storage in Navarro, TX · In queue since July 2023 · Proposed COD April 2030
150.52 MW
Capacity
1
Components
Battery
3y 4m
In Queue
IA Executed
IA Phase
Signed Feb 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 7m
IA → COD
5y 2m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2030-04-18
Projected COD moved
8 times
Apr 2026 → Apr 2030
Net change
+48 months
first report to latest
Capacity
151 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Standard Generation Interconnection Agreement executed between Oncor Electric Delivery Company LLC and Cape Rich BESS LLC
interchange.puc.texas.govExpected commercial operation date per LBNL queue filing
cleanview.coResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0180/cape-rich-bess
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
- ercot.com/files/docs/2025/03/07/CapacityChangesbyFuelTypeCharts_February_2025.xlsx
- cleanview.co/power-projects/developers/navitas-energy
Commercial operation date: LBNL queue snapshot shows April 2028 COD. ERCOT capacity chart (Feb 2025) lists 2027 target, but this appears to be a generic year placeholder. No developer press releases or financing announcements found to confirm actual target date.
Developer: LBNL filing entity is 'Cape Rich BESS LLC' (confirmed in PUC Interchange filings with Oncor). Cleanview lists 'Navitas Energy' as developer in their pipeline page, but this is the only mention and lacks corroboration from press releases or corporate announcements. Cannot confirm operating parent with confidence.
Status: LBNL shows IA executed 2025-02-03. PUC Interchange confirms Standard Generation Interconnection Agreement between Oncor and Cape Rich BESS LLC. Interconnection.fyi newsletter (March 2025) confirms IA date added February 2, 2025.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Cape Rich BESS project is a proposed 150.52 MW battery storage project located in Navarro County, Texas. The developer is listed as Cape Rich BESS. It is currently in the ERCOT interconnection queue as entry ERCOT-26INR0180, with a queue entry date of July 10, 2023. The project's proposed commercial operation date is April 17, 2028, and its interconnection agreement status is currently in the Facility Study phase.
The project consists of 150.52 MW of battery storage capacity. The point of interconnection is the 3387 Revolution Switch 138kV. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cape Rich BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3387 Revolution Switch 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.