Lazy U Solar 1
252 MW generation in Hardeman, TX · In queue since August 2023 · Proposed COD June 2029
252 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-30
Projected COD moved
2 times
Jul 2026 → Jun 2029
Net change
+35 months
first report to latest
Capacity
252 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
COD target updated from June 30, 2027 to June 29, 2029
interconnectionfyi.substack.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-26inr0171
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-442
- bizapedia.com/tx/lazy-u-solar-1-llc.html
- eia.gov/electricity/monthly/xls/table_6_05.xlsx
Commercial operation date: LBNL queue snapshot shows proposed COD of 2029-06-30. Interconnection Weekly (Feb 2025) confirms this date was updated from June 30, 2027 to June 29, 2029, indicating the developer pushed back the timeline. No other independent sources provide alternative dates.
Developer: LBNL filing entity is 'Lazy U Solar 1 LLC' (registered in San Antonio, TX per Bizapedia). No press releases, corporate announcements, or news coverage identify a parent operating company. This appears to be a project-specific LLC with no publicly disclosed developer/sponsor.
Status: LBNL shows 'active' status in Facility Study phase with no IA date. Interconnection Weekly confirms the project remains in queue with updated COD timeline, indicating ongoing but early-stage development.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Lazy U Solar 1 is a proposed solar generation project located in Hardeman County, Texas. The project, with a total capacity of 252 MW, is being developed by Lazy U Solar 1. It is interconnected within the ERCOT region, having entered the interconnection queue as ERCOT-26INR0171 on August 21, 2023. The proposed commercial operation date is June 30, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The project is linked to the existing Lazy U Solar 1 operating plant (EIA ID 68357). The point of interconnection is Tap 345kV 60505 EDITHCLA7B - 60501 TESLA7A ckt2. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hardeman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lazy U Solar 1
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 60505 EDITHCLA7B - 60501 TESLA7A ckt2
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
- POI Substation
- Quanah Acme Mills Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Lazy U Solar 1
Data-driven briefing on Lazy U Solar 1 — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Lazy U ESS 1
Data-driven briefing on Lazy U Solar 1 — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.