Timberline Solar (ERCOT-26INR0161) — Project Summary

Queue ID
ERCOT-26INR0161
Capacity
201 MW
Technology
Solar+Battery
Status
active
Location
Nacogdoches, TX
Region
ERCOT
Developer
Timberline Renewables, LLC
IA Status
Facility Study

Timberline Solar

ERCOT-26INR0161BetaActiveSolarBatteryERCOTLBNL + Live

201 MW hybrid in Nacogdoches, TX · In queue since August 2023 · Proposed COD October 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

201 MW

Capacity

1

Components

Solar

3y 3m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 2m

Facilities Study50%
Queue EntryAug 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-10-05

Queue history
26INR0161 · 38 monthly ERCOT reports, Aug 2023 – Sep 2026

Projected COD moved

3 times

Feb 2026 → Oct 2029

Net change

+44 months

first report to latest

Capacity

201 → 201 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 14, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
—
From queue filing
Developer in saved assessment
Timberline Renewables, LLC
From queue filing
Status at research time
Active
Active — Facility Study stage per LBNL queue, no public announcements found
Financing
Not recorded
Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: LBNL queue snapshot shows proposed COD of 2029-04-20 for the utility-scale project. No research findings discuss this specific ERCOT interconnection project; all search results refer to GAF Energy's residential solar shingle product line, which is unrelated to the Timberline Solar utility project.

Developer: LBNL filing entity is Timberline Renewables, LLC. Research yielded no information about this developer or the utility-scale project—all results concern GAF Energy's consumer solar shingle product coincidentally also named 'Timberline Solar.' No evidence of shell LLC vs parent company structure.

Status: LBNL status is 'active' with IA status at Facility Study stage. No research findings contradict this or provide updates on the utility-scale project's progress.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Timberline Solar is a proposed 201 MW solar generation project located in Nacogdoches County, Texas. The project, developed by Timberline Renewables, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0161, with a queue entry date of August 14, 2023. The proposed commercial operation date is April 20, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.

The point of interconnection for Timberline Solar is Tap 345 kV 3119 Nacogdoches SE - 3116 Mt Enterprise. Recent news coverage indicates activity related to the project's development.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Nacogdoches

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Timberline Renewables, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345 kV 3119 Nacogdoches SE - 3116 Mt Enterprise

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
K2_DGR1_RN
POI Substation
Nacogdoches Road Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.