Timberline Solar
201 MW hybrid in Nacogdoches, TX · In queue since August 2023 · Proposed COD October 2029
201 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-05
Projected COD moved
3 times
Feb 2026 → Oct 2029
Net change
+44 months
first report to latest
Capacity
201 → 201 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: LBNL queue snapshot shows proposed COD of 2029-04-20 for the utility-scale project. No research findings discuss this specific ERCOT interconnection project; all search results refer to GAF Energy's residential solar shingle product line, which is unrelated to the Timberline Solar utility project.
Developer: LBNL filing entity is Timberline Renewables, LLC. Research yielded no information about this developer or the utility-scale project—all results concern GAF Energy's consumer solar shingle product coincidentally also named 'Timberline Solar.' No evidence of shell LLC vs parent company structure.
Status: LBNL status is 'active' with IA status at Facility Study stage. No research findings contradict this or provide updates on the utility-scale project's progress.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Timberline Solar is a proposed 201 MW solar generation project located in Nacogdoches County, Texas. The project, developed by Timberline Renewables, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0161, with a queue entry date of August 14, 2023. The proposed commercial operation date is April 20, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Timberline Solar is Tap 345 kV 3119 Nacogdoches SE - 3116 Mt Enterprise. Recent news coverage indicates activity related to the project's development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Nacogdoches
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Timberline Renewables, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 3119 Nacogdoches SE - 3116 Mt Enterprise
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- K2_DGR1_RN
- POI Substation
- Nacogdoches Road Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.