Santa Garcias Solar (ERCOT-26INR0143) — Project Summary

Queue ID
ERCOT-26INR0143
Capacity
265 MW
Technology
Solar
Status
active
Location
Kleberg, TX
Region
ERCOT
Developer
Oxy Renewable Energy LLC
IA Status
Facility Study

Santa Garcias Solar

ERCOT-26INR0143BetaActiveSolarERCOTLBNL + Live

265 MW generation in Kleberg, TX · In queue since June 2023 · Proposed COD May 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

265 MW

Capacity

1

Components

Solar

3y 5m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 11m

Facilities Study50%
Queue EntryJun 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-05-30

Queue history
26INR0143 · 40 monthly ERCOT reports, Jun 2023 – Sep 2026

Projected COD moved

3 times

May 2026 → May 2029

Net change

+36 months

first report to latest

Capacity

265 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 28, 2023
Interconnection agreement signedDec 31, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
May 30, 2028
Differs from queue: May 30, 2029From queue filing
Developer in saved assessment
Oxy Renewable Energy LLC
From queue filing
Status at research time
Active
Active — in Facility Study phase with interconnection agreements being filed at Texas PUC as of February 2026
Financing
Not recorded

Milestones in this assessment

IA executedFeb 2026Latest in this assessment

Second Amended and Restated ERCOT Standard Generation Interconnection Agreement filed with AEP Texas

interchange.puc.texas.gov
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. cleanview.co/power-projects/planned/solar-farms/texas/26INR0143/santa-garcias-solar
  2. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=FilingParty&SortOrder=Ascending
  3. ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx
  4. ercotqueue.com/project/26INR0143

Commercial operation date: Only LBNL queue data provides a COD target of May 2028. No news sources or press releases confirm or contradict this date. Project is in early Facility Study stage with no construction announcements.

Developer: All sources consistently identify Oxy Renewable Energy LLC as the developer. No evidence of shell LLC structure or parent company differentiation. Texas PUC filings confirm Oxy Renewable Energy LLC as the contracting entity for interconnection agreements.

Status: LBNL status is Active with Facility Study in progress. Texas PUC filings from January-February 2026 show ongoing ERCOT Standard Generation Interconnection Agreement filings with AEP Texas and Oncor, confirming active development.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Santa Garcias Solar project is a proposed 265 MW solar generation facility in Kleberg County, Texas. Developed by Oxy Renewable Energy LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0143, with a queue entry date of June 28, 2023.

The proposed commercial operation date for the Santa Garcias Solar project is May 30, 2028. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 8515 Alazan - 8458 Barney Davis.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Kleberg

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Oxy Renewable Energy LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 8515 Alazan - 8458 Barney Davis

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
SANTACRU_ALL
POI Substation
Alazan Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.