Myers Solar
101.59 MW hybrid in Bee, TX · In queue since June 2023 · Proposed COD May 2028
101.59 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-22
Projected COD moved
2 times
Sep 2026 → May 2028
Net change
+20 months
first report to latest
Capacity
101 → 102 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Research sources and reasoning (6 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/solar-farms/texas/68172_MYEPV/myers-solar-and-storage
- gem.wiki/Myers_Solar_and_Storage_solar_farm
- interconnection.fyi/eia/project/68172-myepv
- mbrweb.ferc.gov/SearchlkpEIA/Index?page=824
- eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_05
- ercotqueue.com/project/26INR0134
Commercial operation date: LBNL proposes May 2028, but Cleanview (an industry aggregator) reports August 2028 expected online date. The 3-month difference is minor and likely reflects updated developer guidance post-queue filing.
Developer: LBNL filing uses 'BT Myers Solar, LLC' (project LLC). FERC MBR and EIA filings consistently show 'Belltown Power Texas 2, LLC' as the operating entity, indicating Belltown Power is the parent developer using project-specific LLCs.
Status: LBNL status 'active' confirmed by ERCOT queue tracker and EIA regulatory status. No construction or financing announcements found; project remains in interconnection study phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Myers Solar is a proposed 100.94 MW solar generation project located in Bee County, Texas. The developer is BT Myers Solar, LLC. The project is listed in the ERCOT interconnection queue as entry ERCOT-26INR0134, with a queue entry date of June 28, 2023, and a proposed commercial operation date of May 22, 2028. Its interconnection status is currently listed as "Facility Study".
The Myers Solar project has been the subject of recent news coverage, with seven articles published across industry, grid, and regulatory categories.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bee
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Myers Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8629 Baez 69 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.