Amerada Storage
150.78 MW generation in Freestone, TX · In queue since May 2023 · Proposed COD July 2028
150.78 MW
Capacity
1
Components
Battery
3y 6m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-21
Projected COD moved
2 times
Oct 2026 → Jul 2028
Net change
+21 months
first report to latest
Capacity
151 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Proposed completion changed from October 21, 2026 to August 22, 2027
interconnectionfyi.substack.comProposed completion date updated to July 20, 2028 (previously August 22, 2027)
interconnectionfyi.substack.comResearch sources and reasoning (6 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-26inr0084
- renewablesinfo.org/project/ercot-26inr0084-amerada-storage
- interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-ad5
- ercotqueue.com/project/26INR0084
- ercotqueue.com/developer/amerada-solar-llc
Commercial operation date: LBNL proposed COD of 2028-07-21 aligns with the most recent interconnection.fyi update (April 2025) showing 'Proposed completion changed to July 20, 2028'. No contradictory signals found in research.
Developer: All sources consistently identify 'Amerada Solar, LLC' as both the filing entity and operating developer. No evidence of shell-LLC structure or parent company differentiation found in any research.
Status: LBNL status 'active' confirmed by multiple queue-tracking sources. Project remains in Facility Study phase with no interconnection agreement as of April 2025.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Amerada Storage project is a proposed 150.78 MW battery energy storage system located in Freestone County, Texas. The project, being developed by Amerada Solar, LLC, is interconnected within the Electric Reliability Council of Texas (ERCOT) region. It entered the ERCOT interconnection queue as project ERCOT-26INR0084 on May 15, 2023, with a proposed commercial operation date of July 21, 2028. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection for the Amerada Storage project is Tap 345kV 3133 RICHLND2_5 - 3381 BIGBRNW_5. Recent news coverage has discussed the development project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Freestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Amerada Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3133 RICHLND2_5 - 3381 BIGBRNW_5
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FREC
- POI Substation
- Richland Chambers Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.