Pin Peaking Energy Center 1 (TEF- Due Diligence)
228 MW generation in Freestone, TX · In queue since April 2023 · Proposed COD May 2026
228 MW
Capacity
1
Components
Gas
3y 7m
In Queue
IA Executed
IA Phase
Signed May 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 1m
IA → COD
2 years
Total Duration
1y 1m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2026-05-01
Projected COD moved
1 time
May 2026 → May 2026
Net change
0 months
first report to latest
Capacity
228 MW
unchanged in the reports
Latest stage
Commercial operation
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Commercial operation date target maintained in ERCOT January 2026 capacity planning
ercot.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- latitudemedia.com/news/the-texas-energy-funds-first-projects-are-coming-online/
- interchange.puc.texas.gov/Documents/21072_96_1580126.PDF
- ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx
- ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025_PlannedMonthly.xlsx
- ercotqueue.com/developer/pin-oak-creek-energy-center-llc
Commercial operation date: LBNL proposed COD of May 2026 is consistently confirmed across multiple ERCOT capacity planning documents from 2025-2026, with no contradictory signals from news or other sources.
Developer: Only LBNL filing entity exists in all sources. No parent company, operating entity, or ownership structure information found in news or research. The LLC name appears to be the actual developer, not a shell entity.
Status: LBNL shows 'active' with IA executed. Project appears in ERCOT capacity planning charts through early 2026 with consistent May 2026 COD. TEF designation indicates Texas Energy Fund involvement for dispatchable generation.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Calpine Freestone Peaker 1 (TEF -Due Diligence) project is a proposed 228 MW gas-fired generation project located in Freestone County, Texas. The developer is Freestone Power Generation, LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-26INR0049, with a queue entry date of April 19, 2023, and a proposed commercial operation date of May 1, 2026.
The project's interconnection agreement (IA) has been executed as of May 30, 2024. The point of interconnection (POI) is the 3134 RICHLAND CHAMBERS 345kV (PSS/E Bus Name: RICHLND1_5) substation. The project is currently listed as active in the interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Mar 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Freestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
PIN OAK CREEK ENERGY CENTER, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3134 RICHLAND CHAMBERS 345kV (PSS/E Bus Name: RICHLND1_5)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Pin Oak Creek Energy Center, LLC
Data-driven briefing on Pin Oak Creek Energy Center, LLC — fleet, generation, financial, and news signals.
Energy Center
Data-driven briefing on Energy Center — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.