LUND STORAGE CENTER 1 (ERCOT-26INR0045) — Project Summary

Queue ID
ERCOT-26INR0045
Capacity
407.55 MW
Technology
Battery
Status
active
Location
Bastrop, TX
Region
ERCOT
Developer
Lund Storage Center 1, LLC
IA Status
Facility Study

LUND STORAGE CENTER 1

ERCOT-26INR0045BetaActiveBatteryERCOTLBNL + Live

407.55 MW storage in Bastrop, TX · In queue since January 2023 · Proposed COD October 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

407.55 MW

Capacity

1

Components

Battery

3y 10m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 9m

Facilities Study50%
Queue EntryJan 17, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-10-31

Queue history
26INR0045 · 41 monthly ERCOT reports, May 2023 – Sep 2026

Projected COD moved

2 times

Dec 2026 → Oct 2029

Net change

+34 months

first report to latest

Capacity

408 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 17, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Oct 31, 2029
From queue filing
Developer in saved assessment
BESS Power Corporation
Filed as Lund Storage Center 1, LLC
Status at research time
Active
Active in the ERCOT queue at Facility Study stage. ERCOT confirmed 407.55 MW in mid-2023. No construction or IA execution has been announced, and BESS Power appears to be developing it toward a sale.
Financing
Not recorded
Ownership history
  1. 2023-01·Undisclosed seller of the SPV→BESS Power Corporationredelfi.com

Milestones in this assessment

Ownership changeJan 2023Latest in this assessment

BESS Power Corp. (65% controlled by Redelfi/Altea) acquired the SPV Lund Storage Center 1 LLC, a roughly 400 MW standalone BESS project in Texas.

redelfi.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. prnewswire.com/news-releases/bess-power-corporation-reaches-its-first-milestone-ercot-confirms-the-capacity-of-lund-storage-project-for-a-total-power-of-407-55-mw-301868754.html
  2. redelfi.com/en/press-releases/bess-power-corp-acquires-a-400-mw-project-for-the-development-of-battery-energy-storage-systems-stand-alone-the-pipeline-reaches-600-mw-of-total-capacity/
  3. ilsole24ore.com/art/egm-raggi-x-redelfi-punta-batterie-e-comunita-energetiche-rinnovabili-AFatNYZB
  4. ercotqueue.com/developer/lund-storage-center-1-llc
  5. interconnection.fyi/projects/state/TX

Commercial operation date: No news or press release gives a COD target. The only date is the LBNL/ERCOT proposed COD of 2029-10-31, and the project is still at Facility Study stage.

Developer: A July 2023 PR Newswire release says BESS Power purchased the US SPV Lund Storage Center 1 LLC. Redelfi and Altea press coverage describes BESS Power as 65% controlled by Redelfi/Altea Green Power. The LBNL filing entity is that project SPV.

Status: LBNL and the interconnection.fyi and ercotqueue.com listings all show the project as active with no commissioned or dropped projects. No source reports construction, an executed IA, or withdrawal.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Lund Storage Center 1 project is a proposed 407.55 MW battery storage project located in Bastrop County, Texas. Developed by Lund Storage Center 1, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-26INR0045. The project entered the interconnection queue on January 17, 2023, and has a proposed commercial operation date of December 31, 2028. Its interconnection status is currently in the Facility Study phase.

The development project consists solely of battery storage with a total capacity of 407.55 MW. Recent news coverage indicates industry interest in the project.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Bastrop

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Lund Storage Center 1, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

TAP 138 KV LINE AND CREATE NEW BUS BETWEEN KIMBRO (7337) AND ELGIN SWITCH (3650)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.