Becerra Creek Storage 1
125.62 MW storage in Webb, TX · In queue since September 2022 · Proposed COD December 2027
125.62 MW
Capacity
1
Components
Battery
3y 10m
In Queue
Facility Study
IA Phase
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
System Study completed, Facility Interconnection Study started as of May 2024, no IA executed
sourceThe Becerra Creek Storage 1 project is a proposed 125.62 MW battery storage project located in Webb County, Texas. Developed by Bordas Renewable Energy, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-26INR0024 on September 21, 2022. The current interconnection status is listed as Facility Study, with a proposed commercial operation date of December 1, 2027.
The project consists of 125.62 MW of battery storage capacity. The point of interconnection is the 345 kV Cenizo Substation (#80220). The project is currently listed as active within the ERCOT queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bordas Renewable Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Cenizo Substation (#80220)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Cenizo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Becerra Creek Storage 1Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.