PHOTON SOLAR 4 SLF
105.98 MW generation in Wharton, TX · In queue since September 2024 · Proposed COD May 2026
105.98 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 8m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-11
Projected COD moved
5 times
Dec 2025 → May 2026
Net change
+5 months
first report to latest
Capacity
106 MW
unchanged in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Proposed completion date revised from December 2024 to June 2025
interconnectionfyi.substack.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
- ercotqueue.com/developer/gulfstar-power-llc
- cleanview.co/power-projects/planned/solar-farms/texas/25INR0673/photon-solar-4-slf
- interconnection.fyi/project/ercot-25inr0673
Commercial operation date: LBNL proposed COD of May 2026 appears stale. Interconnection.fyi newsletter (March 2025) reports proposed completion changed from December 2024 to June 2025, indicating a more current target date approximately 11 months earlier than LBNL snapshot.
Developer: LBNL filing entity 'GulfStar Power, LLC' appears to be the operating company name, not a project-specific shell LLC. All sources consistently reference GulfStar Power, LLC as the developer with no evidence of a parent/subsidiary structure.
Status: LBNL status 'active' at Facility Study stage is confirmed by multiple aggregator sources. Ercotqueue.com shows project as 'Commissioned' at 100% which appears to be a data error given the Facility Study status and future COD.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The PHOTON SOLAR 4 SLF project is a proposed 105.98 MW solar generation facility in Wharton County, Texas. Developed by GulfStar Power, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0673, with a queue entry date of September 4, 2024.
The proposed commercial operation date for PHOTON SOLAR 4 SLF is February 16, 2026. The project's interconnection status is currently in the Facility Study phase.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
GulfStar Power, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44880 Waterh_POI_5 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
PHOTON SOLAR 4 SLF
Data-driven briefing on PHOTON SOLAR 4 SLF — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
GulfStar Power, LLC
Data-driven briefing on GulfStar Power, LLC — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.