Carolina Storage Wichita Falls
202 MW storage in Archer, TX · In queue since February 2024 · Proposed COD August 2028
202 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
Projected COD moved
3 times
Dec 2025 → Aug 2028
Net change
+32 months
first report to latest
Capacity
202 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Project entered ERCOT interconnection queue
cleanview.coResearch sources and reasoning (5 recorded sources)
low confidence at research time
- texomashomepage.com/news/local-news/new-energy-storage-facility-proposed-at-county-commissioners-court/
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0628/carolina-storage-wichita-falls
- interconnection.fyi/project/ercot-25inr0628
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-db7
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
Commercial operation date: LBNL queue snapshot shows proposed COD of August 2028. One search result (Result 7) mentions a COD change from September 2027 to an unspecified later date, but provides no concrete updated target. No press releases or developer announcements found with alternative dates.
Developer: LBNL lists 'CSE Storage, LLC' as developer. No press releases, corporate announcements, or news coverage found identifying a parent company or operating entity. Result 2 mentions 'Solvent Energy Incorporated' proposing a storage facility in Wichita Falls in April 2024, but no confirmation this is the same project or that Solvent is the parent of CSE Storage.
Status: LBNL status is 'active' with IA status at 'Facility Study' stage. No news coverage found announcing construction start, financing close, or project withdrawal. Result 8 (May 2024 spreadsheet) confirms 'SS Started, FIS Started, No IA' status.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Carolina Storage Wichita Falls is a proposed 202 MW battery storage project located in Wichita County, Texas. The project, developed by CSE Storage, LLC, is currently in the ERCOT interconnection queue as entry ERCOT-25INR0628, with a queue entry date of February 26, 2024. The proposed commercial operation date is August 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 202 MW of battery storage capacity. The point of interconnection is Tap 345kV 1422 Bowman - 1458 Cobb Switch. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Archer
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CSE Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1422 Bowman - 1458 Cobb Switch
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Bowman Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.