Anagram Solar
130.56 MW generation in Live Oak, TX · In queue since April 2024 · Proposed COD December 2027
130.56 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Anagram Solar is a proposed 130.56 MW solar generation project located in Live Oak County, Texas. The development project, sponsored by Anagram Solar, entered the ERCOT interconnection queue as ERCOT-25INR0621 on April 9, 2024. Its proposed commercial operation date is December 31, 2027. The project's interconnection status is currently in the Facility Study phase.
The Anagram Solar project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Live Oak
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Anagram Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8156 Charter 138 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Anagram SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.