Bobcat Bluff Storage SLF (ERCOT-25INR0616) — Project Summary

Queue ID
ERCOT-25INR0616
Capacity
—
Technology
Battery
Status
active
Location
Archer, TX
Region
ERCOT
Developer
Cub Storage LLC
IA Status
—

Bobcat Bluff Storage SLF

ERCOT-25INR0616BetaActiveOtherBattery Energy StorageERCOTLive · ERCOT

— hybrid in Archer, TX · In queue since February 2024 · Proposed COD April 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

—

Capacity

0

Components

2y 8m

In Queue

—

IA Status

Signed Jan 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 11m

IA → COD

1y 3m

Total Duration

1y 11m

Construction0%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 12, 2026

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-04-15

About

Bobcat Bluff Storage SLF is a proposed battery energy storage development project in Archer County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by Cub Storage LLC and is classified as a hybrid project. Its technology components are listed as battery energy storage and an additional component categorized as "Other." The project's total capacity is not specified in the available data. It is proposed to connect to the grid at the 1475 Windthorst 138 kV point of interconnection.

The project entered the ERCOT interconnection queue on February 27, 2024, under queue ID ERCOT-25INR0616, and its status is active. An interconnection agreement was executed on January 12, 2026. The project's proposed commercial operation date is April 15, 2027.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Archer

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Cub Storage LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

1475 Windthorst 138 kV

Data Source

Live · ERCOT

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Bobcat Bluff Storage SLF
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.