Zeus Armstrong Solar (ERCOT-25INR0586) — Project Summary

Queue ID
ERCOT-25INR0586
Capacity
503.56 MW
Technology
Solar+Battery
Status
active
Location
Armstrong, TX
Region
ERCOT
Developer
Armstrong Solar, LLC
IA Status
Facility Study

Zeus Armstrong Solar

ERCOT-25INR0586BetaActiveSolarBatteryERCOTLBNL + Live

503.56 MW hybrid in Armstrong, TX · In queue since May 2024 · Proposed COD April 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

503.56 MW

Capacity

1

Components

Solar

2y 6m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 11m

Facilities Study50%
Queue EntryMay 20, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-17

Queue history
25INR0586 · 26 monthly ERCOT reports, Aug 2024 – Sep 2026

Projected COD moved

1 time

May 2026 → Apr 2028

Net change

+23 months

first report to latest

Capacity

510 → 504 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 20, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 17, 2028
From queue filing
Developer in saved assessment
Armstrong Solar, LLC
From queue filing
Status at research time
Active
Active — ERCOT study status as of 2026-09-01 is SS completed, Facility Study (FIS) started, no IA executed; no evidence of construction.
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. app.nrgmap.com/queues/ercot-25inr0586
  2. interconnection.fyi/project/ercot-25inr0586
  3. ercotqueue.com/project/25INR0586
  4. cleanview.co/power-projects/planned/solar-farms/texas/25INR0586/zeus-armstrong-solar
  5. futuregrid.io/genprojects/zeus-armstrong-solar/

Commercial operation date: Every source that gives a date repeats the queue's proposed online date. NRG Map, mirroring ERCOT status data as of 2026-09-01, shows 'Proposed online 2028-04-17', and Cleanview and FutureGrid say 'expected online 2028'. These look derived from the queue data, and no developer press release or financing-backed target was found.

Developer: ERCOT-derived trackers (NRG Map, ercotqueue.com, interconnection.fyi, Infrasure) all list Armstrong Solar, LLC. FutureGrid names 'Zeus Renewable Energy Development' as operator, but that is an unverified aggregator claim with no corroborating press release, so I did not treat it as a parent.

Status: NRG Map (ERCOT data, fetched 2026-09-29) shows 'Status active' and 'SS Completed, FIS Started, No IA'. ercotqueue.com's 'Currently Construction' label conflicts with the absence of an interconnection agreement and any construction announcement, so I did not adopt it.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Zeus Armstrong Solar project is a proposed solar generation facility with a total capacity of 509.6 MW. It is located in Armstrong County, Texas, and is being developed by Armstrong Solar, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0586, with a queue entry date of May 20, 2024.

The proposed commercial operation date for the Zeus Armstrong Solar project is April 17, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345KV 23900 AlLIBATES -23914 TULECNYN. The project has appeared in recent news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Armstrong

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Armstrong Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345KV 23900 AlLIBATES -23914 TULECNYN

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.