Blue Creek Energy Storage
101.2 MW storage in Wharton, TX · In queue since October 2023 · Proposed COD December 2028
101.2 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Projected COD moved
2 times
Sep 2025 → Dec 2028
Net change
+39 months
first report to latest
Capacity
101 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue at Facility Study stage
cleanview.coResearch sources and reasoning (2 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0545/blue-creek-energy-storage
- cleanview.co/developer/hexagon-energy
Commercial operation date: LBNL queue snapshot shows proposed COD of 2028-12-31. No independent news sources found discussing this specific project's timeline, so LBNL date stands as the only available reference.
Developer: LBNL filing entity is 'Blue Creek Energy Storage, LLC' (project-specific shell). Cleanview database lists this project under Hexagon Energy's development pipeline, identifying Hexagon as the operating parent company.
Status: LBNL shows 'active' status at Facility Study stage (pre-IA execution). No news coverage indicates construction activity or permitting milestones; project appears to be in standard early-queue progression.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Blue Creek Energy Storage, LLC is proposing a 101.2 MW battery storage project in Wharton County, Texas. The project, identified as ERCOT-25INR0545 in the ERCOT interconnection queue, entered the queue on October 13, 2023, and has a proposed commercial operation date of December 31, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 101.2 MW of battery storage capacity. Recent news coverage indicates regulatory interest in the development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Blue Creek Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 42985 DYANN_POI8 - 43190 S_LANE_B138 Ckt 60
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Blue Creek Energy StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.