Kahla Storage (ERCOT-25INR0513) — Project Summary

Queue ID
ERCOT-25INR0513
Capacity
200.9 MW
Technology
Battery
Status
active
Location
Leon, TX
Region
ERCOT
Developer
BT Kahla Storage, LLC
IA Status
Facility Study

Kahla Storage

ERCOT-25INR0513BetaActiveBatteryERCOTLBNL + Live

200.9 MW storage in Leon, TX · In queue since August 2023 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

200.9 MW

Capacity

1

Components

Battery

3y 3m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 4m

Facilities Study50%
Queue EntryAug 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-29

Queue history
25INR0513 · 38 monthly ERCOT reports, Aug 2023 – Sep 2026

Projected COD moved

2 times

Dec 2025 → Dec 2028

Net change

+36 months

first report to latest

Capacity

201 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 21, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 29, 2028
From queue filing
Developer in saved assessment
Belltown Power Texas 2, LLC
Filed as BT Kahla Storage, LLC
Status at research time
Active
Active — Facility Study stage, no IA executed. Regulatory approvals pending per EIA, not yet under construction.
Financing
Not recorded

Milestones in this assessment

COD targetApr 29, 2026

Original proposed COD before being pushed to December 2028

interconnectionfyi.substack.com
COD targetDec 28, 2028Latest in this assessment

Revised proposed completion date as of December 2024

interconnectionfyi.substack.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_05
  2. interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
  3. bizapedia.com/tx/bt-kahla-storage-llc.html
  4. ercotqueue.com/project/25INR0513

Commercial operation date: LBNL queue shows proposed COD of 2028-12-29. One interconnection.fyi digest from Dec 2024 notes the COD was pushed from April 2026 to December 2028, confirming the current LBNL date. No developer press releases or financing announcements found to provide an updated target.

Developer: LBNL filing entity is 'BT Kahla Storage, LLC' (project LLC formed June 2023 per Bizapedia). EIA Monthly Electric Power data lists the owner as 'Belltown Power Texas 2, LLC', indicating BT is a shell entity for the Belltown parent company.

Status: LBNL shows 'active' status at Facility Study stage with no IA date. EIA confirms regulatory approvals pending and project not under construction. No withdrawal or suspension signals found.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Kahla Storage project is a proposed 200.9 MW battery storage project located in Leon County, Texas. Developed by BT Kahla Storage, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0513. The project entered the interconnection queue on August 21, 2023, and has a proposed commercial operation date of December 29, 2028. Its interconnection status is currently in the Facility Study phase.

The Kahla Storage project is linked to the existing Kahla Storage operating plant (EIA ID 68168). The point of interconnection is Tap 345kV 46020 Limestone 967 Gibbons Creek Circuit 50. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Leon

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BT Kahla Storage, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 46020 Limestone 967 Gibbons Creek Circuit 50

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW
POI Substation
Farrar Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.