Vault Solar
108.5 MW generation in Palo Pinto, TX · In queue since June 2023 · Proposed COD December 2027
108.5 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Projected COD moved
2 times
Oct 2025 → Dec 2027
Net change
+26 months
first report to latest
Capacity
109 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Queue application submitted to ERCOT, Facility Study stage
cleanview.coResearch sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: Only LBNL queue data provides a COD estimate of 2027-12-31. No news coverage or press releases found for this specific project to validate or update this date.
Developer: LBNL lists 'PPM THR Solar' as developer. No news coverage found to identify if this is a shell LLC or confirm parent company. Search results returned unrelated Energy Vault storage projects and residential solar companies, but nothing on Vault Solar in Palo Pinto County.
Status: LBNL status is 'active' at Facility Study stage. No contradicting information found in search results, which returned no project-specific news.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Vault Solar is a proposed solar generation project located in Palo Pinto County, Texas, within the ERCOT region. The development project, with a total capacity of 108.5 MW, is being pursued by PPM THR Solar. It consists of 108.5 MW of solar photovoltaic generation.
The project entered the ERCOT interconnection queue as entry ERCOT-25INR0482 on June 28, 2023, and has a proposed commercial operation date of December 31, 2027. Its interconnection status is currently in the Facility Study phase. The project has been mentioned in recent news articles.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Palo Pinto
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
PPM THR Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap #331 Rwmiller - #320 Jaybird 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.