Castle Corral BESS (ERCOT-25INR0475) — Project Summary

Queue ID
ERCOT-25INR0475
Capacity
200.9 MW
Technology
Battery
Status
suspended
Location
Mills, TX
Region
ERCOT
Developer
—
IA Status
—

Castle Corral BESS

ERCOT-25INR0475BetaSuspendedBatteryERCOTLBNL + Live

200.9 MW storage in Mills, TX · In queue since July 2023 · Proposed COD September 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

200.9 MW

Capacity

1

Components

Battery

3y 4m

In Queue

—

IA Status

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 2m

Suspended0%
Queue EntryJul 30, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-14

Queue history
25INR0475 · 27 monthly ERCOT reports, Jul 2023 – Sep 2025

Projected COD moved

3 times

Jun 2025 → Mar 2028

Net change

+33 months

first report to latest

Capacity

201 → 201 MW

changed in the reports

Latest stage

Facilities study done

last listed Sep 2025

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 31, 2023
Facilities study approvedJun 18, 2025
On ERCOT's inactive listOct 2025 – Sep 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Castle Corral BESS project is a proposed 201.1 MW battery storage project located in Mills County, Texas. Developed by Castle Corral BESS, LLC, the project consists of 201.1 MW of battery capacity. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0475, with a queue entry date of July 31, 2023.

The proposed commercial operation date for the Castle Corral BESS project is August 23, 2027. The project's interconnection status is currently in the Facility Study phase, and it intends to interconnect at the 345 kV Russell Gap Switching Station Bus #3348. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Mills

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

—

Utility

—

Entity

ERCOT

Service Type

—

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.