Crowded Star I BESS (ERCOT-25INR0473) — Project Summary

Queue ID
ERCOT-25INR0473
Capacity
202.69 MW
Technology
Solar+Battery
Status
active
Location
Jones, TX
Region
ERCOT
Developer
Jones City Solar II, LLC
IA Status
IA Executed

Crowded Star I BESS

ERCOT-25INR0473BetaActiveBatteryBatteryERCOTLBNL + Live

202.69 MW generation in Jones, TX · In queue since August 2023 · Proposed COD July 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

202.69 MW

Capacity

1

Components

Battery

3y 3m

In Queue

IA Executed

IA Phase

Signed Dec 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 4m

IA → COD

1y 7m

Total Duration

2y 4m

Construction75%
Queue EntryAug 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 1, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-07-09

Queue history
25INR0473 · 37 monthly ERCOT reports, Aug 2023 – Sep 2026

Projected COD moved

4 times

Dec 2025 → Jul 2027

Net change

+19 months

first report to latest

Capacity

101 → 203 MW

changed in the reports

Latest stage

Cancelled

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 21, 2023
Facilities study approvedNov 10, 2025
Interconnection agreement signedDec 1, 2025
CancelledJun 30, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Jul 2027
From queue filing
Developer in saved assessment
Jones City Solar II, LLC
From queue filing
Status at research time
Active
Active — IA executed December 2025, no construction announcements yet
Financing
Not recorded

Milestones in this assessment

IA executedDec 1, 2025Latest in this assessment

Interconnection Agreement executed with ERCOT

ercot.com
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. ercot.com/files/docs/2026/01/08/Capacity-Changes-by-Fuel-Type-Charts_December_2025.xlsx
  2. ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
  3. cleanview.co/planned-battery-projects/TX/25INR0473/crowded-star-i-bess

Commercial operation date: LBNL queue snapshot shows proposed COD of 2027-07-09, confirmed by ERCOT capacity chart (Jul-27) and Texas PUC generating plants list. No contradictory signals from news or press releases.

Developer: Only source is LBNL filing entity 'Jones City Solar II, LLC'. No press releases, corporate announcements, or news coverage identifying a parent company or operating entity. Unable to determine if this is a shell LLC or operating company.

Status: LBNL shows 'active' status with IA executed 2025-12-01. No news coverage of this specific project found. ERCOT capacity chart confirms project remains in queue for 2027.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Crowded Star I BESS project is a proposed 202.69 MW battery storage project located in Jones County, Texas. Developed by Jones City Solar II, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0473. It entered the interconnection queue on August 21, 2023, and has a proposed commercial operation date of July 9, 2027. The project's interconnection status is currently in the Facility Study phase.

The Crowded Star I BESS development has been the subject of recent news coverage, with four articles published related to deals, regulatory matters, and industry news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Jones

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Jones City Solar II, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

68014 Open Sky

Data Source

LBNL + Live

DeveloperPrologis EnergyEnergy-Storage.News · 2025-06-19
AgencyKendall County Fire MarshalBoerne Star · 2024-06-22
RulingNoticeBoerne Star · 2024-06-22
TransactionDivestitureEnergy-Storage.News · 2025-06-19
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-03-26

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.