Old Sorrell Energy Storage
43.1 MW storage in Concho, TX · In queue since June 2023
43.1 MW
Capacity
1
Components
Battery
3y 1m
In Queue
—
IA Status
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Old Sorrell Energy Storage is a proposed 43.1 MW battery storage project located in Concho County, Texas. The project is being developed by Rocky Mountain Energy Holdings, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-25INR0459, with a queue entry date of June 28, 2023.
The proposed commercial operation date for Old Sorrell Energy Storage is January 10, 2028. The project's interconnection agreement status is currently in the Facility Study phase. The point of interconnection is Tap 69kV 6372 Eden - 6376 Colorado River Municipal Water #1.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Concho
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Eden Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Old Sorrell Energy StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.