Dios BESS
201.08 MW storage in Jackson, TX · In queue since May 2023 · Proposed COD December 2027
201.08 MW
Capacity
1
Components
Battery
3y 6m
In Queue
IA Executed
IA Phase
Signed Apr 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 11m
IA → COD
2y 8m
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2027-12-31
Projected COD moved
2 times
Dec 2025 → Dec 2027
Net change
+24 months
first report to latest
Capacity
201 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
ERCOT Standard Generation Interconnection Agreement filed with Texas PUC between AEP Texas Inc. and Dios BESS, LLC
interchange.puc.texas.govExpected online date per Cleanview interconnection tracker
cleanview.coResearch sources and reasoning (5 recorded sources)
high confidence at research time
- cleanview.co/planned-battery-projects/TX/67918_DIOS/dios-bess-llc
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2114
- elibrary.ferc.gov/eLibrary/docinfo?accession_Number=20250609-3045&sid=3f2fa233-444b-4e87-a5c4-0277499c4be4
- ercotqueue.com/project/25INR0441
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-db7
Commercial operation date: LBNL queue shows 2027-12-31, but Cleanview (a specialized interconnection tracker) reports expected online date of February 2027 and March 2027 in separate listings. The ~10-month difference is typical queue-date lag.
Developer: All sources consistently identify 'Dios BESS, LLC' as the developer with no parent company or operating entity disclosed. No press releases, acquisitions, or corporate announcements found to indicate a shell-LLC structure or parent organization.
Status: LBNL status 'IA Executed' confirmed by Texas PUC filing (Case 35077-2114) showing ERCOT Standard Generation Interconnection Agreement between AEP Texas Inc. and Dios BESS, LLC filed 4/21/2025, with FERC acceptance letter dated 6/9/2025.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Dios BESS project is a proposed 201.08 MW battery storage project located in Jackson County, Texas. Developed by Dios BESS, LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-25INR0441, with a queue entry date of May 15, 2023, and a proposed commercial operation date of December 31, 2027. The project's interconnection agreement status is currently in the Facility Study phase.
The Dios BESS project is linked to an existing operating facility, Dios BESS, LLC (EIA ID 67918). The point of interconnection is the 8117 GANADO138kV substation. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jackson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dios BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8117 GANADO138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- POI Substation
- Ganado Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.