Purple Sage BESS 1
156 MW storage in Collin, TX · In queue since March 2023 · Proposed COD February 2028
156 MW
Capacity
1
Components
Battery
3y 8m
In Queue
IA Executed
IA Phase
Signed Oct 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 7m
IA → COD
3y 4m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-02-12
Projected COD moved
3 times
May 2025 → Feb 2028
Net change
+33 months
first report to latest
Capacity
150 → 156 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Target commercial operation date per ERCOT capacity tracking
ercot.comResearch sources and reasoning (9 recorded sources)
high confidence at research time
- comptroller.texas.gov/economy/fiscal-notes/infrastructure/2024/battery-store/
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0391/purple-sage-bess-1
- interconnection.fyi/project/ercot-25inr0391
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ercot.com/files/docs/2025/03/07/CapacityChangesbyFuelTypeCharts_February_2025.xlsx
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
- ercot.com/files/docs/2025/07/09/Capacity-Changes-by-Fuel-Type-Charts_June_2025.xlsx
- ercotqueue.com/developer/purple-sage-llc
- facebook.com/groups/erathcountystopsolarfarmshere/posts/1505477940161889/
Commercial operation date: LBNL queue snapshot shows proposed COD of 2027-05-30. Multiple ERCOT capacity tracking spreadsheets (Feb 2025, June 2025) confirm 2027 target. No contradictory news sources found.
Developer: LBNL filing entity is 'Purple Sage, LLC' (project shell). Texas PUC filing (Result 12) explicitly identifies 'RWE Solar Development, LLC' as the actual developer for Purple Sage BESS 1 & 2, indicating RWE is the parent operating company.
Status: LBNL shows 'active' status with IA executed 2024-10-11. ERCOTqueue.com (Result 11) confirms 'IA + FIS complete' at 86% progress. No withdrawal or suspension signals.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Purple Sage BESS 1 is a proposed 156 MW battery storage project located in Collin County, Texas. The project, developed by Purple Sage, LLC, is interconnected within the ERCOT region under queue ID ERCOT-25INR0391. The project entered the interconnection queue on March 8, 2023, with a proposed commercial operation date of May 30, 2027.
The project's Interconnection Agreement (IA) has been executed as of October 11, 2024. The point of interconnection (POI) is the Anna 345 kV Bus# 2373. The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Collin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Purple Sage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Anna 345 kV Bus# 2373.
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.