HappyDogSolar
85.54 MW hybrid in Milam, TX · In queue since June 2023 · Proposed COD August 2027
85.54 MW
Capacity
1
Components
Solar
3y 5m
In Queue
IA Executed
IA Phase
Signed Dec 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 6m
IA → COD
2y 8m
Total Duration
1y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-08-04
Projected COD moved
3 times
Jul 2025 → Aug 2027
Net change
+25 months
first report to latest
Capacity
86 → 86 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
HappyDogSolar is a proposed solar generation project located in Milam County, Texas, with a total capacity of 85.54 MW. Developed by Rosula Solar LLC, the project entered the ERCOT interconnection queue as ERCOT-25INR0382 on June 7, 2023. The proposed commercial operation date is April 13, 2027.
The project's interconnection agreement (IA) was executed on December 16, 2024. The point of interconnection (POI) is Tap 345kV 3704 Hog Creek Switch _x0013_ 3687 Bell County East Switch. The project is currently listed as active in the ERCOT queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rosula Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3704 Hog Creek Switch – 3687 Bell County East Switch
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.