Elan BESS
202.65 MW storage in Fort Bend, TX · In queue since March 2023 · Proposed COD December 2026
202.65 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
Projected COD moved
1 time
Dec 2025 → Dec 2026
Net change
+12 months
first report to latest
Capacity
203 MW
unchanged in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Fort Bend County tax abatement agreement signed for Elan BESS project
agendalink.fortbendcountytx.govResearch sources and reasoning (2 recorded sources)
medium confidence at research time
- agendalink.fortbendcountytx.gov/mindocs/2024/CCTR/20240312_3879/3666_33_signed_agreement_-.pdf
- cleanview.co/power-projects/developers/sunraycer-assets
Commercial operation date: LBNL queue snapshot shows proposed COD of 2026-12-31. No independent news sources or press releases found to confirm or contradict this date; all search results merely echo the LBNL filing data.
Developer: Fort Bend County tax abatement agreement (March 2024) identifies 'Sunraycer Assets I. LLC' as the developer of the Elan BESS project, while LBNL filing uses the project-specific shell entity 'Elan BESS, LLC'.
Status: LBNL shows 'active' status at Facility Study stage. No news of withdrawal, suspension, or construction start found in search results.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Elan BESS is a proposed 202.65 MW battery storage project located in Fort Bend County, Texas. Developed by Elan BESS, LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0372, with a queue entry date of March 8, 2023, and a proposed commercial operation date of December 31, 2026. The project's interconnection status is currently in the Facility Study phase, and its point of interconnection is the 42380 Needville 138kV substation.
The Elan BESS project has appeared in recent news coverage regarding energy storage development in the ERCOT region.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Fort Bend
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Elan BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
42380 Needville 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Needville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Elan BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.