Willis Storage
176.13 MW storage in Rains, TX · In queue since March 2023 · Proposed COD May 2028
176.13 MW
Capacity
1
Components
Battery
3y 8m
In Queue
IA Executed
IA Phase
Signed Apr 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 1m
IA → COD
3y 1m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-05-31
Projected COD moved
4 times
Dec 2025 → May 2028
Net change
+29 months
first report to latest
Capacity
178 → 176 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Proposed commercial operation date per ERCOT queue
cleanview.coResearch sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0370/willis-storage
- renewablesinfo.org/plant/68176-willis-storage
- facebook.com/groups/hrollinscommunitynews/posts/1966995240554899/
Commercial operation date: LBNL queue filing shows proposed COD of August 13, 2027. No independent news sources provide alternative dates; Cleanview aggregator mirrors LBNL data.
Developer: LBNL filing uses 'BT Majewski Storage LLC' (project shell). Renewablesinfo.org identifies operating entity as 'Belltown Power Texas 2, LLC' — 'BT' likely abbreviates Belltown.
Status: LBNL shows 'active' status with IA executed April 7, 2025. No news of withdrawal, construction start, or operational status found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Willis Storage project is a proposed 176.13 MW battery storage project located in Rains County, Texas. Developed by BT Willis Storage, LLC, the project is currently in the ERCOT interconnection queue as entry ERCOT-25INR0370, with a queue entry date of March 27, 2023. The proposed commercial operation date is August 13, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The Willis Storage project has been the subject of recent news coverage, with 10 articles related to the project appearing in the news. These articles primarily focus on grid-related topics, with additional coverage of industry, development, and regulatory aspects.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Rains
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT Majewski Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV Emory North 3171 to Liberty POD 1723
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesWillis Storage
Data-driven briefing on Willis Storage — fleet, generation, financial, and news signals.
What's the status of the 1 queue project linked to Willis Storage?
Data-driven briefing on Willis Storage — fleet, generation, financial, and news signals.
NY Chateaugay 0 Willis Rd Storage Battery Storage in NYISO (New York) in New York growth signals — PPAs, construction, new projects
Data-driven briefing on Willis Storage — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.