Echols Grove, LLC (ERCOT-25INR0368) — Project Summary

Queue ID
ERCOT-25INR0368
Capacity
201.15 MW
Technology
Solar
Status
active
Location
Lamar, TX
Region
ERCOT
Developer
Echols Grove, LLC
IA Status
IA Executed

Echols Grove, LLC

ERCOT-25INR0368BetaActiveSolarERCOTLBNL + Live

201.15 MW generation in Lamar, TX · In queue since April 2023 · Proposed COD June 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

201.15 MW

Capacity

1

Components

Solar

3y 7m

In Queue

IA Executed

IA Phase

Signed Jul 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 3m

IA → COD

2y 11m

Total Duration

1y 3m

Construction75%
Queue EntryApr 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 6, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-06-30

Queue history
25INR0368 · 42 monthly ERCOT reports, Mar 2023 – Sep 2026

Projected COD moved

7 times

Dec 2025 → Jun 2027

Net change

+18 months

first report to latest

Capacity

204 → 202 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedApr 7, 2023
Facilities study approvedJun 18, 2026
Interconnection agreement signedJul 6, 2024
On ERCOT's inactive listNov 2024 – Nov 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2026
Differs from queue: Jun 30, 2027
Developer in saved assessment
Zelestra
Filed as Echols Grove, LLC
Status at research time
IA Executed
IA Executed — construction commenced March 2026, financing closed, Meta PPA secured
Financing
Secured
$600 million green financing credit facility closed March 2026 for 440 MW Texas portfolio (Echols Grove + Cedar Range), backed by Meta PPAs

Milestones in this assessment

IA executedJul 6, 2024

Interconnection Agreement executed with Oncor Electric Delivery

interchange.puc.texas.gov
GroundbreakingMar 5, 2026

Construction commenced on Echols Grove (253 MWdc) with McCarthy Building as lead EPC

finance.yahoo.com
Financing closeMar 25, 2026Latest in this assessment

$600M green financing facility secured for 440 MW portfolio including Echols Grove

businesswire.com
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. finance.yahoo.com/news/zelestra-proceeds-construction-echols-grove-150000756.html
  2. businesswire.com/news/home/20260325337645/en/Zelestra-Secures-%24600-Million-Green-Financing-for-440-MW-Texas-Solar-Portfolio-Backed-by-Meta-PPAs
  3. solarpowerworldonline.com/2026/03/meta-signs-ppa-on-441-mw-texas-solar-project-portfolio/
  4. interchange.puc.texas.gov/Documents/35077_2335_1567263.PDF

Commercial operation date: LBNL proposed COD is April 2027, but Zelestra announced construction commencement in March 2026 with financing closed and Meta PPA secured. Construction-start timing suggests 2026-2027 online date, aligning closer to LBNL but with active development underway.

Developer: LBNL filing entity is 'Echols Grove, LLC' (project SPV). Multiple March 2026 press releases identify Zelestra as the developer proceeding with construction and securing financing for this project as part of their 440 MW Texas portfolio.

Status: LBNL status 'Active' with IA executed July 2024 is accurate. Ground reality shows project advanced to construction phase in March 2026 with $600M financing facility and Meta offtake agreement.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Echols Creek Solar is a proposed 201.15 MW solar generation project located in Lamar County, Texas. Developed by BT Ferguson Solar, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-25INR0368. The project entered the interconnection queue on April 7, 2023, and has a proposed commercial operation date of April 3, 2027. Its interconnection status is currently in the Facility Study phase.

The proposed project is linked to the existing Echols Creek Solar operating plant (EIA plant ID 68902). Recent news coverage has highlighted the project, with articles appearing in the "deals" and "industry" categories.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Lamar

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Echols Grove, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV Hawk Hollow Switch (#11768) and Lamar Blossom Switch (#11770)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.