Marshall Spring Storage
150 MW generation in Gillespie, TX · In queue since February 2023 · Proposed COD December 2028
150 MW
Capacity
1
Components
Battery
3y 9m
In Queue
Facility Study
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 10m
IA → COD
3 years
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-20
Projected COD moved
2 times
Jun 2026 → Dec 2028
Net change
+30 months
first report to latest
Capacity
150 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Gillespie County commissioners passed resolution opposing BESS projects including Peregrine's facility
energy-storage.newsGillespie County filed petition to intervene in lawsuit over safety and water concerns
fredericksburgstandard.comLBNL reports IA date of 2025-12-26 with Facility Study status
renewablesinfo.orgResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- ketk.com/news/local-news/peregrine-energy-plans-400m-battery-storage-in-east-texas/
- energy-storage.news/texas-county-passes-resolution-opposing-bess-house-of-representatives-considers-regulations/
- fredericksburgstandard.com/2025/12/03/county-joins-bess-facility-suit/
- renewablesinfo.org/project/ercot-25inr0354-marshall-spring-storage
- ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx
Commercial operation date: LBNL proposes 2026-07-01 COD. No independent sources confirm or update this target; ERCOT spreadsheet lists 2026 but no month. No press releases or financing announcements provide alternate timeline.
Developer: LBNL filing uses project LLC 'Marshall Springs Storage, LLC'. News extraction and Energy-Storage.News (Mar 2025) both identify Peregrine Energy Solutions as the operating developer behind the project.
Status: LBNL status is 'active' with Facility Study in progress. However, Energy-Storage.News and Fredericksburg Standard report significant local resistance including county resolution opposing battery storage and legal intervention, indicating project faces regulatory/community hurdles.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Marshall Spring Storage is a proposed 150 MW battery storage project located in Gillespie County, Texas. Developed by Marshall Springs Storage, LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-25INR0354, with a queue entry date of February 20, 2023. The proposed commercial operation date is July 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection (POI) is planned at a new station between the 7132 L_GILLES8_1Y - 7126 L_FERGUS8_1Y 138kV line and the 7132 L_GILLES8_1Y - 7128 L_HORSBA8_1Y 138kV line, looping both lines into the new POI station. The development project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Gillespie
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Marshall Springs Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
New POI station between 7132 L_GILLES8_1Y - 7126 L_FERGUS8_1Y 138kV line and 7132 L_GILLES8_1Y - 7128 L_HORSBA8_1Y 138kV line, then loop in both lines into the new POI station.
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesMarshall Spring Storage
Data-driven briefing on Marshall Spring Storage — fleet, generation, financial, and news signals.
Marshall (MI)
Data-driven briefing on Marshall — fleet, generation, financial, and news signals.
Marshall
Data-driven briefing on Marshall — fleet, generation, financial, and news signals.
Marshall (IL)
Data-driven briefing on Marshall — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.