Marshall Spring Solar (ERCOT-25INR0353) — Project Summary

Queue ID
ERCOT-25INR0353
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Gillespie, TX
Region
ERCOT
Developer
Marshall Springs Solar, LLC
IA Status
Facility Study

Marshall Spring Solar

ERCOT-25INR0353BetaActiveSolarBatteryERCOTLBNL + Live

150 MW hybrid in Gillespie, TX · In queue since February 2023 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

150 MW

Capacity

1

Components

Solar

3y 9m

In Queue

Facility Study

IA Phase

Signed Dec 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 10m

IA → COD

3 years

Total Duration

2y 10m

Construction50%
Queue EntryFeb 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 26, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-12-20

Queue history
25INR0353 · 36 monthly ERCOT reports, Oct 2023 – Sep 2026

Projected COD moved

2 times

Jun 2026 → Dec 2028

Net change

+30 months

first report to latest

Capacity

150 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 20, 2023
Interconnection agreement signedDec 26, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 2y 5m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestonesolar panels installed, power inverters being installedmarshallindependent.com · 2024-06-11
Expected CODQ3 2024marshallindependent.com · 2024-06-11
Delay reasondelivery of materialsmarshallindependent.com · 2024-06-11

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jul 2026
Differs from queue: Dec 20, 2028From queue filing
Developer in saved assessment
Marshall Springs Solar, LLC
From queue filing
Status at research time
Active
Active — facing organized local opposition over environmental and safety concerns; no construction or financing announcements
Financing
Not recorded

Milestones in this assessment

Permit approvedDec 2025

Gillespie County filed petition to intervene in lawsuit over BESS facility safety and water concerns

fredericksburgstandard.com
IA executedDec 26, 2025Latest in this assessment

LBNL queue shows IA date of December 26, 2025 (Facility Study phase)

interconnection.fyi
Research sources and reasoning (6 recorded sources)

low confidence at research time

  1. mysanantonio.com/news/hill-country/article/gillespie-county-solar-battery-projects-21230815.php
  2. fredericksburgstandard.com/2025/12/03/county-joins-bess-facility-suit/
  3. energy-storage.news/texas-county-passes-resolution-opposing-bess-house-of-representatives-considers-regulations/
  4. fightfbgsolar.com/
  5. interconnection.fyi/project/ercot-25inr0353
  6. cleanview.co/power-projects/planned/solar-farms/texas

Commercial operation date: LBNL queue filing shows July 2026 COD target. No independent news sources confirm or update this date; only third-party aggregators (Interconnection.fyi, CleanView) echo the LBNL data. Project faces significant local opposition but no public announcements of delays.

Developer: Only LBNL filing identifies the developer as 'Marshall Springs Solar, LLC'. No press releases, corporate announcements, or news coverage reveal a parent company or operating entity. Local opposition websites and news articles reference the project but not the developer's identity.

Status: LBNL status is 'active' in Facility Study phase. Multiple Dec 2025 news articles document Gillespie County residents and commissioners opposing the project through resolutions and legal intervention, but no withdrawal or suspension has been filed.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Marshall Spring Solar is a proposed 150 MW solar generation project located in Gillespie County, Texas. The project, developed by Marshall Springs Solar, LLC, is currently in the ERCOT interconnection queue as entry ERCOT-25INR0353, with a queue entry date of February 20, 2023. The proposed commercial operation date is July 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.

The point of interconnection (POI) is planned at a new POI station between the 7132 L_GILLES8_1Y - 7126 L_FERGUS8_1Y 138kV line and the 7132 L_GILLES8_1Y - 7128 L_HORSBA8_1Y 138kV line, with both lines looped into the new POI station. The project has been mentioned in recent news coverage related to the energy industry.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Gillespie

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Marshall Springs Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

New POI station between 7132 L_GILLES8_1Y - 7126 L_FERGUS8_1Y 138kV line and 7132 L_GILLES8_1Y - 7128 L_HORSBA8_1Y 138kV line, then loop in both lines into the new POI station.

Data Source

LBNL + Live

DeveloperMissouri River Energy Servicesmarshallindependent.com · 2024-06-11
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26