Fort Concho Energy storage (ERCOT-25INR0339) — Project Summary

Queue ID
ERCOT-25INR0339
Capacity
251.15 MW
Technology
Battery
Status
active
Location
Tom Green, TX
Region
ERCOT
Developer
Rocky Mountain Energy Development, LLC
IA Status
Facility Study

Fort Concho Energy storage

ERCOT-25INR0339BetaActiveBatteryERCOTLBNL + Live

251.15 MW storage in Tom Green, TX · In queue since January 2023 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

251.15 MW

Capacity

1

Components

Battery

3y 10m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 11m

Facilities Study50%
Queue EntryJan 30, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Queue history
25INR0339 · 44 monthly ERCOT reports, Feb 2023 – Sep 2026

Projected COD moved

2 times

Feb 2026 → Dec 2028

Net change

+34 months

first report to latest

Capacity

251 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 30, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 31, 2028
From queue filing
Developer in saved assessment
Castlelake
Filed as Rocky Mountain Energy Development, LLC
Status at research time
Active
Active — Facility Study stage, no construction timeline announced publicly
Financing
Not recorded

Milestones in this assessment

IA executedJan 2023Latest in this assessment

Entered ERCOT queue as 25INR0339, Facility Study stage

cleanview.co
Research sources and reasoning (3 recorded sources)

medium confidence at research time

  1. cleanview.co/power-projects/developers/castlelake
  2. cleanview.co/developer/castlelake
  3. ercotqueue.com/developer/rocky-mountain-energy-development-llc

Commercial operation date: Only LBNL queue snapshot provides a COD of 2028-12-31. No independent news sources or press releases confirm or update this target date.

Developer: LBNL filing entity is 'Rocky Mountain Energy Development, LLC' (project-specific LLC). Cleanview pipeline listings show this project under Castlelake's development portfolio, indicating Castlelake is the parent/operating company.

Status: LBNL reports 'active' status at Facility Study stage. No news coverage indicates construction start, financing close, or withdrawal. Project remains in early interconnection-study phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Fort Concho Energy storage project is a proposed 251.15 MW battery storage project located in Tom Green County, Texas. Developed by Rocky Mountain Energy Development, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-25INR0339, with a queue entry date of January 30, 2023. The proposed commercial operation date is December 31, 2028.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138 kV #76320 Schkade - #76011 Twin Buttes Line; LCRA.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Tom Green

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Rocky Mountain Energy Development, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138 kV #76320 Schkade - #76011 Twin Buttes Line; LCRA

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.