Star Dairy Storage
204.93 MW generation in Lamar, TX · In queue since April 2023 · Proposed COD July 2027
204.93 MW
Capacity
1
Components
Battery
3y 7m
In Queue
IA Executed
IA Phase
Signed Dec 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 8m
IA → COD
2y 7m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2027-07-12
Projected COD moved
4 times
Mar 2026 → Jul 2027
Net change
+16 months
first report to latest
Capacity
209 → 205 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Target commercial operation date per PUC Texas generation table
ftp.puc.texas.govResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025_PlannedMonthly.xlsx
- ftp.puc.texas.gov/public/puct-info/industry/electric/reports/genplant/gentable.xls
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0334/star-dairy-storage
Commercial operation date: LBNL queue shows April 2027 COD with IA executed Dec 2024. Multiple ERCOT planning documents (Nov 2025 capacity chart, PUC Texas gen table) confirm 2027 target. No contradicting news sources found.
Developer: LBNL filing entity is 'Star Dairy Storage' which appears to be a project-specific LLC. No press releases, corporate announcements, or news coverage identify the parent developer or operating company behind this project.
Status: LBNL shows 'active' status with IA executed Dec 9, 2024. ERCOT capacity planning documents from Nov 2025 continue to list project with 2027 target, indicating no withdrawal or suspension.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Star Dairy Storage (ERCOT queue ID 25INR0334) is a proposed energy development project in Lamar County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Developed by an entity also named Star Dairy Storage, the project has a total capacity of 204.93 MW. Although the queue classifies its technology as Solar+Battery, the only component listed is battery energy storage, accounting for the full 204.93 MW. The project is categorized as a generation project and plans to interconnect at a tap on the 345 kV line between the PARIS_SW1_5 (1692) and WOODARD_5 (11699) substations.
The project entered the ERCOT interconnection queue on April 19, 2023, and holds an active status. It executed an interconnection agreement on December 9, 2024, a significant milestone in the ERCOT interconnection process. The proposed commercial operation date is July 12, 2027.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Star Dairy Storage
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1692 PARIS_SW1_5 -- 11699 WOODARD_5
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Star Dairy Storage
Data-driven briefing on Star Dairy Storage — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.